background image

INSTALLATION

Specifications for this unit in residential new construction market
require the outdoor unit, indoor unit, refrigerant tubing sets,
metering device, and filter drier listed in presale literature. There
can be no deviation. Consult the Application Guideline and
Service Manual — Residential Split-System Air Conditioners and
Heat Pumps using Puron® Refrigerant to obtain required unit
changes for specific applications and for R-22 retrofit.

Step 1—Check Equipment and Job Site

UNPACK UNIT

Move to final location. Remove carton taking care not to damage
unit.

INSPECT EQUIPMENT

File claim with shipping company prior to installation if shipment
is damaged or incomplete. Locate unit rating plate on unit corner
panel. It contains information needed to properly install unit.
Check rating plate to be sure unit matches job specifications.

Step 2—Install On a Solid, Level Mounting Pad

If conditions or local codes require the unit be attached to pad, tie
down bolts should be used and fastened through knockouts
provided in unit base pan. Refer to unit mounting pattern in Fig. 3
to determine base pan size and knockout hole location.

On rooftop applications, mount on level platform or frame. Place
unit above a load-bearing wall and isolate unit and tubing set from
structure. Arrange supporting members to adequately support unit
and minimize transmission of vibration to building. Consult local
codes governing rooftop applications.

Roof mounted units exposed to winds above 5 mph may require
wind baffles. Consult the Application Guideline and Service
Manual — Residential Split-System Air Conditioners and Heat
Pumps using Puron® Refrigerant for wind baffle construction.

NOTE:

Unit must be level to within ± 2° (± 3/8 in./ft) per

compressor manufacturer specifications.

Step 3—Clearance Requirements

When installing, allow sufficient space for airflow clearance,
wiring, refrigerant piping, and service. Allow 30-in. clearance to
service end of unit and 48 in. above unit. For proper airflow, a 6-in.
clearance on 1 side of unit and 12 in. on all remaining sides must

be maintained. Maintain a distance of 24 in. between units.
Position so water, snow, or ice from roof or eaves cannot fall
directly on unit.

Step 4—Operating Ambients

The minimum outdoor operating ambient in cooling mode is 55°F,
and the maximum outdoor operating ambient in cooling mode is
125°F.

Step 5—Check Indoor AccuRater® Piston and
Install Piston Ring (38EZA Standard)

If unit is to be installed with a piston metering device, proceed as
follows:

1. Check indoor coil piston to see if it matches the required

piston shown on outdoor unit rating plate. If it does not match,
replace indoor coil piston with piston shipped with outdoor
unit. The piston shipped with outdoor unit is correct for any
approved indoor coil combination.

2. After correct piston is installed, locate Teflon piston ring

shipped in piston bag. Install piston ring behind metering
piston as shown in Fig. 4. The piston ring ensures that piston
stays seated during all operating conditions.

NOTE:

If a Puron TXV is used with a Puron reciprocating

compressor, an appropriate accessory hard start kit (capacitor and
relay) must be used. For the appropriate accessory hard start kit see
the Product Data Digest.

Step 6—TXV Installation (38ETA and 38ESA Required)
NOTE:

All 38ETA and 38ESA units MUST be installed with a

hard shut off Puron® TXV.

The thermostatic expansion valve is specifically designed to
operate with Puron®. Do not use an R-22 TXV. An existing R-22
TXV must be replaced with a factory-approved TXV specifically
designed for Puron®. To replace an R-22 TXV, refer to Installa-
tion Instructions packaged with accessory kit.

NOTE:

FK4 and FC4 fan coils are equipped with an R-22 TXV.

If an FK4 or an FC4 fan coil is used with a Puron® air conditioner,
the R-22 TXV must be replaced with a Puron® TXV.

Fig. 2—Connecting Tubing Installation

A01383

INSULATION

VAPOR TUBE

LIQUID TUBE

OUTDOOR WALL

INDOOR WALL

LIQUID TUBE

VAPOR TUBE

INSULATION

CAULK

Avoid contact between tubing and structure

NOTE:

THROUGH THE WALL

HANGER STRAP

(AROUND VAPOR

TUBE ONLY)

JOIST

1

 MIN.

SUSPENSION

Fig. 3—Mounting Unit to Pad

DIMENSIONS (IN.)

UNIT BASE PAN

DIMENSIONS

TIEDOWN KNOCKOUT LOCATIONS

A

B

C

22-1/2 X 22-1/2

3-11/16

18-1/8

14-3/8

30 X 30

6-1/2

23-1/2

20

A94199

C

B

A

3

8

D. (9.53) TIEDOWN 

KNOCKOUTS (2) PLACES

2

Содержание 38ESA

Страница 1: ...erate at higher pressures than standard R 22 systems Do not use R 22 service equipment or com ponents on Puron equipment INSTALLATION RECOMMENDATIONS NOTE In some cases noise in the living area has been traced to gas pulsations from improper installation of equipment 1 Locate unit away from windows patios decks etc where unit operation sound may disturb customer 2 Ensure that vapor and liquid tube...

Страница 2: ...must be maintained Maintain a distance of 24 in between units Position so water snow or ice from roof or eaves cannot fall directly on unit Step 4 Operating Ambients The minimum outdoor operating ambient in cooling mode is 55 F and the maximum outdoor operating ambient in cooling mode is 125 F Step 5 Check Indoor AccuRater Piston and Install Piston Ring 38EZA Standard If unit is to be installed wi...

Страница 3: ...revent damage to tubing 5 Using wire cutters cut equalizer tube off flush with vapor tube inside cabinet 6 Remove bulb from vapor tube inside cabinet 7 Braze equalizer stub tube closed Use protective barrier as necessary to prevent damage to drain pan IMPORTANT Route the equalizer tube of Puron TXV through suction line connection opening in fitting panel prior to replacing fitting panel around tub...

Страница 4: ...ubing and indoor coil are now ready for leak testing This check should include all field and factory joints EVACUATE REFRIGERANT TUBING AND INDOOR COIL Never use the system compressor as a vacuum pump Refrigerant tubes and indoor coil should be evacuated using the recommended deep vacuum method of 500 microns The alternate triple evacuation method may be used if the procedure outlined below is fol...

Страница 5: ...be Diameter Connection Diameter Tube Diameter Connection Diameter Tube Diameter 018 024 3 8 3 8 5 8 5 8 5 8 3 4 030 036 3 8 3 8 3 4 3 4 3 4 7 8 042 048 3 8 3 8 7 8 7 8 7 8 1 1 8 060 3 8 3 8 7 8 1 1 8 7 8 1 1 8 NOTES 1 Tube diameters are for lengths up to 50 ft For tubing lengths greater than 50 ft horizontal or greater than 20 ft vertical differential consult the Application Guideline and Service ...

Страница 6: ...l Electrical Accessories Refer to the individual instructions packaged with kits or acces sories when installing Step 11 Start Up To prevent compressor damage or personal injury observe the following Do not overcharge system with refrigerant Do not operate unit in a vacuum or at negative pressure Do not vent refrigerant to atmosphere Recover during system repair or final unit disposal Do not disab...

Страница 7: ...y relay circuit the indoor blower runs an additional 90 sec to increase system efficiency Step 12 Check Charge UNIT CHARGE Factory charge and charging method are shown on unit informa tion plate Charge Puron units using a commercial type metering device in manifold hose Charge refrigerant into suction line NOTE If superheat or subcooling charging conditions are not favorable charge must be weighed...

Страница 8: ...on note superheat 7 Refer to Table 6 Find superheat temperature located in item 6 and suction pressure At this intersection note suction line temperature 8 If a unit has a higher suction line temperature than charted temperature add refrigerant until charted temperature is reached 9 If unit has a lower suction line temperature than charted temperature reclaim refrigerant until charted temperature ...

Страница 9: ...3 55 57 59 10 45 47 49 51 53 55 57 59 61 12 47 49 51 53 55 57 59 61 63 14 49 51 53 55 57 59 61 63 65 16 51 53 55 57 59 61 63 65 67 18 53 55 57 59 61 63 65 67 69 20 55 57 59 61 63 65 67 69 71 22 57 59 61 63 65 67 69 71 73 24 59 61 63 65 67 69 71 73 75 26 61 63 65 67 69 71 73 75 77 28 63 65 67 69 71 73 75 77 79 30 65 67 69 71 73 75 77 79 81 32 67 69 71 73 75 77 79 81 83 34 69 71 73 75 77 79 81 83 85...

Страница 10: ...CONDITIONER C INDOOR FAN HEAT STAGE 1 COOL STAGE 1 C SEE NOTE 2 G A97367 24 VAC HOT 24 VAC COM R C G W W1 Y Y2 R C C CARRIER NON PROGRAMMABLE THERMOSTAT MODEL AC FA FB FC FD FF FX FAN COIL AIR CONDITIONER SEE NOTE 2 G W2 HEAT STAGE 1 COOL STAGE 1 INDOOR FAN A97594 24 VAC HOT R G W W1 Y Y2 O W2 R W2 C B S1 S2 CARRIER PROGRAMMABLE THERMOSTAT MODEL AC FA FB FC FD FF FX FAN COIL AIR CONDITIONER G Y1 W...

Страница 11: ...AN COIL AIR CONDITIONER G Y1 W2 L INDOOR FAN HEAT STAGE 1 COOL STAGE 1 NOT USED 24 VAC COM NOT USED NOT USED NOT USED OPTIONAL OUTDOOR SENSOR CONNECTION C Y1 O C SEE NOTE 2 J2 JUMPER J1 JUMPER A97597 WIRING DIAGRAM NOTES 1 CARRIER THERMOSTAT WIRING DIAGRAMS ARE ONLY ACCURATE FOR MODEL NUMBERS TSTAT _______ 2 WIRING MUST CONFORM TO NEC OR LOCAL CODES 3 SOME UNITS ARE EQUIPPED WITH PRESSURE SWITCH E...

Страница 12: ...riers with rated working pressures less than 600 psig Do not install a suction line filter drier in liquid line POE oils absorb moisture rapidly Do not expose oil to atmosphere Poe oils may cause damage to certain plastics and roofing materials Wrap all filter driers and service valves with wet cloth when brazing A factory approved liquid line filter drier is required on every unit Do not use an R...

Отзывы: