Depending on the installation and control type, each unit can
control its own water pump. If there is only one common pump
for the two units, the master unit can control this. In this case
shut-off valves must be installed on each unit. They will be
activated at the opening and closing by the control of each unit
(and the valves will be controlled using the dedicated water
pump outputs).

30RY 017 to 080 (standard configuration: return water

control)

2

1

Legend

1

Master unit

2

Slave unit

Additional CCN board (one per unit, with connection via communication
bus)

Control boxes of the master and slave units

Water inlet

Water outlet

Water pumps for each unit (included as standard for units with hydronic

module)
Additional sensors for leaving water control, to be connected to channel 1
of the slave boards of each master and slave unit
CCN communication bus
Connection of two additional sensors

30RY 017 to 080 (with configuration: leaving water

control)

1

2

11 - START-UP

11.1 - Preliminary checks

-

Never be tempted to start the chiller without reading fully,
and understanding, the operating instructions and without
having carried out the following pre-start checks:

-

Check the chilled water circulation pumps, air handling
units and all other equipment connected to the eva-
porator.

-

Refer to the manufacturer's instructions.

-

For units without hydronic module, the water pump
overheat protection device must be connected in series
with the pump contactor power supply. If the pump is not
supplied with the unit (unit without hydronic module),
verify that the power input of the field-installed pump
does not exceed the rating of the standard pump contactor,
supplied in the control box (max. 3 kW).

-

Refer to the wiring diagram supplied with the unit.

-

Ensure that there are no refrigerant leaks.

-

Confirm that all pipe securing bands are tight.

-

Confirm the the electrical connections are secure.

11.2 - Actual start-up

IMPORTANT

Commissioning and start-up of the chiller must be
supervised by a qualified refrigeration engineer.

It is strictly forbidden to energise the units, if the fan has
not been connected to a duct system.

The outdoor installation option includes a protection
grille that does not require this connection.

Start-up and operating tests must be carried out with a
thermal load applied and water circulating in the
evaporator.

All set-point adjustments and control tests must be
carried out before the unit is started up.

Please refer to the Controls manual for these units.

The unit should be started up in Local ON mode.
Ensure that all safety devices are satisfied, especially the high
pressure switches.

11.3 - Operation of two units in master/slave mode

The control of a master/slave assembly is in the entering water
and does not require any additional sensors (standard confi-
guration).

All parameters, required for the master/slave function must be
configured using the Service Configuration menu. All remote
controls of the master/slave assembly (start/stop, set point, load
shedding etc.) are controlled by the unit configured as master
and must only be applied to the master unit.

Содержание 30RY 017

Страница 1: ...Installation operation and maintenance instructions AQUASNAP For the operation of the control please refer to the Pro Dialog Control manual for the 30RA RH 30RY RYH B series Carrier is participating...

Страница 2: ...loop volume 12 6 6 30RY unit operating range at full and part load 12 6 7 Pressure drop in the plate heat exchangers 13 7 ELECTRICAL CONNECTION 14 7 1 Power supply 15 7 2 Voltage phase imbalance 15 8...

Страница 3: ...tual subcooling 24 12 4 Refrigerant guidelines 25 12 5 Recharging liquid refrigerant 25 12 6 Undercharge 25 12 7 Characteristics of R407C 25 12 8 Electrical maintenance 25 12 9 Condenser coil 26 13 AQ...

Страница 4: ...d before operating the unit In certain cases the globe stops are installed on ball valves These valves are factory supplied lead sealed in the open position This system permits isolating and removing...

Страница 5: ...ioration and injuries to people Faults and leaks must be repaired immediately The authorized technician must have the responsibility to repair the fault immediately Each time repairs have been carried...

Страница 6: ...be trapped between this valve and the expansion device This valve is situated on the liquid line before the filter drier box Do not attempt to repair or recondition any safety devices when corrosion o...

Страница 7: ...connections and service operations For the centre of gravity coordinates the position of the unit mounting holes and the weight distribu tion points refer to the certified dimensional drawing supplied...

Страница 8: ...s and arrangements are in place and comply with the current European standard Verify that all document for pressure containers certificates name plates files instruction manuals that are required docu...

Страница 9: ...location of fixing points weight distribution and coordinates of the centre of gravity refer to the certified dimensional drawings B Install a condensate collection channel around the unit or install...

Страница 10: ...070 080 Power circuit Nominal power supply V ph Hz 400 3 50 Voltage range V 360 440 Control circuit supply The control circuit is supplied via the unit mounted transformer Maximum unit power input kW...

Страница 11: ...re range 10 C to 46 C class 4K3 altitude 2000 m presence of hard solids class 4S2 no significant dust present presence of corrosive and polluting substances class 4C2 negligible vibration and shock cl...

Страница 12: ...vaporator T of 2 8 K must be guaranteed which corresponds to a water flow rate of 0 9 l s per kW 6 5 Water loop volume 6 5 1 Minimum water loop volume The minimum water loop volume in litres is given...

Страница 13: ...17 2 30RY 021 3 30RY 026 4 30RY 033 5 30RY 040 6 30RY 050 7 30RY 060 8 30RY 070 9 30RY 080 1 10 100 1000 2000 1 10 1 2 3 4 5 6 7 8 9 6 7 Pressure drop in the plate heat exchangers Pressure drop kPa Wa...

Страница 14: ...ections For copper cables use electrolytic copper AMP type cable stiffeners with 6 mm terminal for sizes 017 to 080 30RY X mm Y mm 017 033 1180 761 040 080 190 762 NOTES The 30RY units have only one p...

Страница 15: ...isolator switch are designed for the number and type of wires listed in the table below The calculations are based on the maximum machine current see electrical data tables and the standard installati...

Страница 16: ...be recommended 10 pH Ideal case pH neutral at 20 25 C 7 pH 8 ATTENTION Charging adding or draining fluid from the water circuit must be done by qualified personnel using air vents and materials suitab...

Страница 17: ...n switching the unit off in winter Add ethylene glycol with an adequate concentration to protect the installation up to a temperature of 10 K below the lowest temperature likely to occur at the instal...

Страница 18: ...c module are equipped with a flow switch and an internal piping heater Legend Components of the unit and hydronic module 1 Victaulic screen filter 2 Expansion tank 3 Safety valve 4 Available pressure...

Страница 19: ...rve to obtain the desired operating point see example for 30RY 080 The pres sure drop reading in the plate heat exchanger is used to control and adjust the nominal system flow rate The pressure drop i...

Страница 20: ...ly closing the control valve until you obtain the specific pressure drop that corresponds to the nominal flow rate at the required unit operating point If the system has an excessive pressure drop in...

Страница 21: ...ide a removable window on the return air duct to permit maintenance of the air temperature sensor 10 5 2 Air return with accessory filter The suction side connection collar must first be removed Insta...

Страница 22: ...ry Filter access for maintenance is ensured by removing the two Metric screws on the unit side rear view of the unit The cover panel supplied with a handle can now be removed The filters are attached...

Страница 23: ...ntactor power supply If the pump is not supplied with the unit unit without hydronic module verify that the power input of the field installed pump does not exceed the rating of the standard pump cont...

Страница 24: ...heck all heat exchangers and all pipework If water jets are used inside the units e g to clean the coils the lower holes for possible condensate removal must be blocked 12 2 Verification of the refrig...

Страница 25: ...specialists Their activities must be overseen and checked by properly trained people To minimise discharge to the atmosphere refrigerants and lubricating oil must be transferred using methods which re...

Страница 26: ...4 51 04 28 75 63 67 67 64 10 22 12 27 77 19 5 46 77 51 55 29 64 07 68 02 10 25 22 94 28 56 19 75 47 29 52 05 29 25 64 47 68 39 12 9 Condenser coil We recommend that finned coils are inspected regularl...

Страница 27: ...operations please refer to the paragraph on diagnostics and breakdowns of the 30RA RH 30RY RYH B Pro Dialog Plus controls manual IMPORTANT Before each equipment maintenance operation please ensure tha...

Страница 28: ...ssors fans and pumps Check the compressor fan and pump winding status Mechanical checks Check the tightening of the fan tower fan compressor and control box fixing bolts Check that no water has penetr...

Страница 29: ...mage prevent unit start up Unit is level in its installation Power supply agrees with the unit name plate Electrical circuit wiring has been sized and installed properly Unit ground wire has been conn...

Страница 30: ...to 080 3 50 litres nominal kW capacity for air conditioning 30RY 017 to 040 Proper loop volume established Proper loop corrosion inhibitor included litres of Proper loop freeze protection included if...

Страница 31: ...this machine Once all checks have been made start the unit in the LOCAL ON position Unit starts and operates properly Temperatures and pressures WARNING Once the machine has been operating for a while...

Страница 32: ...persedes order No 13427 76 04 2002 Manufactured by Carrier SA Montluel France Manufacturer reserves the right to change any product specifications without notice Printed in the Netherlands Printed on...

Отзывы: