Chapter 3: System planning
Site planning
Page 3-11
Note
A restricted access location is defined (in EN 60950-1) as one where access may only be
gained by use of a tool or lock and key, or other means of security, and access is controlled
by the authority responsible for the location. Access must only be gained by persons who
have been instructed about the reasons for the restrictions applied to the location and about
any precautions that must be taken. Examples of permissible restricted access locations are
a lockable equipment room or a lockable cabinet.
ODU wind loading
Ensure that the ODU and the structure on which it is mounted are capable of withstanding the prevalent
wind speeds at a proposed 450 Platform site. Wind speed statistics are available from national
meteorological offices.
The ODU and its mounting bracket are capable of withstanding wind speeds of:
Up to 200 mph (322 kph) for PMP 450m Series – AP 5 GHz
Up to 124 mph (Integrated) for PMP/PTP 450i – all models 3 GHz and 5 GHz
Up to 200 mph (Connectorized) for PMP/PTP 450i – all models 3 GHz and 5 GHz
Up to 200 mph (322 kph) for PMP/PTP 450 – all models
Up to 200 mph (322 kph) for PMP 450 – Ruggedized
Up to 200 mph (322 kph) for PMP 450i – all models 900 MHz
Up to 118 mph (191 kph) for PMP 450b
Up to 90 mph (145 kph) for PMP 450d
Up to 100 mph (161 kph) for 900 MHz antennas
Wind blowing on the ODU will subject the mounting structure to significant lateral force. The magnitude of
the force depends on both wind strength and surface area of the ODU. Wind loading is estimated using
the following formulae:
Force (in kilograms) = 0.1045aV
2
where:
o
“a” is the surface area in square meters, and
o
“V” is the wind speed in meters per second.
Force (in pounds) = 0.0042Av
2
where:
o
“A” is the surface area in square feet, and
o
“v” is the wind speed in miles per hour.
Applying these formulae to the 450 platform at different wind speeds, the resulting wind loadings are
shown in below tables.
Содержание PMP 450 AP
Страница 1: ...33F Cambium 450 Platform User Guide System Release 15 2 pass...
Страница 14: ...Contents Page xii 450m overload I Glossary III...
Страница 91: ...Chapter 2 System hardware System Components Page 2 27 Figure 16 Gigabit Enet Capable power supply...
Страница 104: ...Chapter 2 System hardware Cabling Page 2 40...
Страница 139: ...Chapter 3 System planning Typical deployment Page 3 6 Figure 44 GPS receiver tower or mast installation...
Страница 157: ...Chapter 3 System planning Radio Frequency planning Page 3 24 Figure 49 Sector Antenna...
Страница 158: ...Chapter 3 System planning Radio Frequency planning Page 3 25 Figure 50 cnMedusa Antenna...
Страница 189: ...Chapter 3 System planning Remote AP Deployment Page 3 56 Figure 59 Remote AP wired to SM that serves as a relay...