Chapter 8: Acceptance and Commissioning Procedures
Site Acceptance Procedure
phn-3972 004v000
Page 8-24
Antenna sealing O-Ring is properly fitted and not
damaged
OK
Antenna/Launch unit polarization is as per link
requirements
OK
SITE ACCEPTANCE CHECKLIST
(continued)
4. OUTDOOR UNIT
Type of ODU mount:
(Direct or Remote mount)
ODU is securely mounted to the antenna or pole
OK
ODU is grounded as per installation instructions
OK
ODU
‘s polarization is as per
link requirements
OK
ODU is installed properly and has no physical
damage
OK
For Remote-Mount Only:
Remote mount kit is securely mounted to the pole
OK
Flexible waveguide has no physical damage and
connectors are sealed
OK
All flexible waveguide bolts are secured using
washers and lock-washers, as appropriate
OK
Flexible waveguide is secured to the pole
OK
6. CAT5/Fiber Optic CABLE
Overall cable length:
Cable type:
CAT5 connectors assembled properly on the cable
OK
Cable connected securely to ODU and IDU
OK
Cable connector is covered by gland and secure by
cable tie at the ODU
OK
At the ODU, cable has a service/drip loop to
prevent moisture from entering the connector
OK
Cable is secured using suitable restraints to fixed
points at regular intervals (0.5 m recommended)
OK
Cable has no sharp bends, kinks, or crushed areas.
All bends are per manufacturer specifications
OK
Grounding is as per site specifications
OK
Cable point-of-entry to building/shelter is weather-
proof
OK
Cable ends are properly labeled
OK