FAST-Bi-1K5 – User’s Manual
17
2.
Installation
This chapter contains instructions for initial inspection and preparation for use.
2.1
Preparation for use
In order to be operational, the PS must be connected to an appropriate AC source.
The AC source voltage should be within the PS specification. Do not apply power
before reading
Section 2.2
and
The installation procedure is described in
Step
Checklist
Description
1
Initial inspection
Physical inspection of PS
2
Mounting
Installing the PS, ensuring proper ventilation
3
AC Input Power Connection
Connect the PS to the AC source
5
Load connection
Wire size selection, Remote Sensing
4
First switch-on
Switch-on checkout procedure
Table 2:
Installation checklist
2.2
Initial inspection
Prior to shipment, the PS was inspected and found free either of mechanical or
electrical defects. Upon unpacking of the PS, inspect is suggested for any damage which
may have occurred in transit.
The inspection should confirm that there is no-exterior damage to the PS (e.g.
broken switch or connectors) and all panels and display are not scratched or cracked.
Keep all packaging material until the inspection has been completed. If a damage has
been detected, compile the RMA form available on the CAEN ELS web site.