20
We reserve the right to make any changes due to technical modifications.
Commissioning and maintenance instructions Logano GE434 Gas-fired special boiler • Issue 02/2003
Buderus Heiztechnik GmbH • http://www.heiztechnik.buderus.de
Heating system start-up
6
!
If necessary, disconnect your heating system from
the mains electricity supply.
!
Check the new pipe section, incl. the immediate seal
at the gas train for external leaks. The test pressure
on the gas train inlet must be no higher than
150 mbar.
6.1.4 Purging the gas supply pipe
Carry out the following steps on the l.h. and the r.h. gas
burner.
!
Release the plug on the test port for gas supply
pressure and venting (Fig. 5,
) on the gas train
by two turns, and connect the hose.
!
Slowly open the mains gas shut-off valve.
!
Purge the gas supply pipe.
CAUTION!
SYSTEM DAMAGE
through short circuits.
!
Cover areas at risk before searching for
leaks.
!
Never apply leak detector spray to
cableways, plugs or electrical leads.
Never let any spray drop down onto
such areas.
Fig. 5
Purging the gas supply pipe
Item 1:
Test port for gas supply pressure and venting
1
Содержание Logano GE434
Страница 71: ...71 14 Declaration of conformity ...