14
Taking the heating system out of operation
Logano GC 144 II – 6 720 808 893 (2017/02)
20
14
Taking the heating system out of operation
14.1
Normal system shut-down
▶ Turn ON/OFF switch (emergency shutoff switch) to OFF position.
This shuts off power to the boiler and all of its components (e.g.
burner, temperature controller).
▶ Turn ON/OFF knob on gas valve clockwise to OFF position.
Fig. 29 Emergency shut-down
[1]
ON/OFF switch (Emergency shutoff switch)
14.2
Emergency shut-down procedures
Inform the owner and operator of the procedure in case of emergency:
▶ Never put yourself at risk. Your own safety must always take priority.
▶ Shut off main gas supply.
▶ Shut down the heating system using the boiler emergency shutoff
switch or the corresponding circuit-breaker.
15
Boiler inspection and maintenance
15.1
Why is regular maintenance important?
Heating systems require regular maintenance for the following reasons:
• to maintain high efficiency operation and to operate the heating
system economically (low fuel consumption),
• to sustain safe operation,
• to maintain combustion at an environmentally responsible level.
• to ensure trouble-free operation and long life.
All maintenance work must be carried out by a qualified boiler
technician. When replacing components use only parts approved by
Buderus. Maintenance is required once a year. Record the results of the
inspection in the protocol on page 25.
15.2
Testing the flue system, including combustion air, air
inlets and Ventilation openings
Check the venting system, including the combustion air, inlet and outlet
openings. All faults must be repaired immediately. Make sure that the
combustion air feed and the inlets and outlets are not blocked at any
point.
15.3
Inspection of the boiler and burner
▶ Visually check the boiler and burner for external dirt.
▶ If dirt is found, clean boiler and burner.
15.4
Preparing boiler for cleaning
▶ Take the boiler out of operation (
▶ Open and remove front door of boiler (
▶ Turn gas valve ON/OFF knob clockwise to OFF position. Do not use
force.
NOTICE:
System damage due to freezing.
The heating system can freeze up in cold weather if it is
shut down.
▶ Leave the heating system switched ON constantly as
much as possible.
▶ Protect the heating system from freezing by draining
the boiler and water pipes at the lowest point.
1
6 720
8
04 440-37.1T
Spare parts can be ordered from the spare parts catalog.
WARNING:
Risk to life from electric shock.
▶ Before opening a unit: disconnect electrical power
and lock to prevent accidental reactivation.
WARNING:
Risk to life from explosion of flammable
gases.
▶ Never work on gas lines unless you are licensed for
this type of work
WARNING:
Risk to life from explosion of flammable
gases.
▶ Wait five (5) minutes until all gas residues have
dissipated. Check whether there is any smell of gas,
including at floor level. If there is a gas odor, shut of
main gas valve immediately. Turn off power to the
heating system and call your customer service
technician or gas company.