Delivery and Transport
Site Planning Information BioSpec 70/30 USR_2_V020
79
7
Delivery and Transport
Magnet and electronics installation must always be planned and carried out in close
cooperation with the local Bruker office. On the day the magnet is placed, a Bruker employee
must be on site. Planning of delivery and transport must comprise the following items:
• Magnet transport to installation site, e.g. air and/or road transport with suitable transport
methods.
• Unloading area and magnet transport within the building.
• Appropriate intermediate storage, if necessary.
• Transport and installation of the electronics cabinets and accessories.
WARNING
Warning of personal injury and/or damage to the MR Instrument and/or
building.
Transport, storage, and placement of the MR instrument must be carried out with particular
care. Only trained, qualified, and authorized personnel is allowed to handle the MR
instrument. Occupational standards and minimum safety distances between building
structures and heavy loads must be fulfilled along the entire transport route. The load-
bearing capacity of all transport routes, storage facilities, and installation areas of the
equipment components must be checked and released by professional personnel.
If operations are performed by unqualified personnel, the following risks exist:
u
Personal injury when transporting heavy loads
u
Significant damage to the MR instrument due to inappropriate handling
u
Structural damage to buildings due to heavy loads
If the organization of transportation and placement are not carried out by Bruker, it is the
System Owner's responsibility to take the necessary safety and preventative measures when
transporting and storing the MR instrument and to ensure that there is adequate liability
insurance.
Damage during transportation and loss of transport insurance services:
Before the magnet is unloaded from the truck, the condition of the shock indicators must be
checked and documented.
Содержание BioSpec 70/30 USR V2
Страница 6: ...Contents vi Site Planning Information BioSpec 70 30 USR_2_V020...
Страница 20: ...Safety 20 Site Planning Information BioSpec 70 30 USR_2_V020...
Страница 88: ...Moving or Dismantling the MR Instrument 88 Site Planning Information BioSpec 70 30 USR_2_V020...
Страница 94: ...Checklist in Preparation of the Installation 94 Site Planning Information BioSpec 70 30 USR_2_V020...
Страница 98: ...Tables 98 Site Planning Information BioSpec 70 30 USR_2_V020...
Страница 103: ...Site Planning Information BioSpec 70 30 USR_2_V020 103...
Страница 104: ...Bruker Corporation info bruker com www bruker com Order No Site Planning Information BioSpec 70 30 USR...