BROCK® MEYER® Walkways and Ladders
Installations While the Tower Is on the Tower Trailer
MFH1968-5B
15
Lift the Tower to “First Stage” to Work Underneath
After all possible Walkways and Ladder-and-Cage sections have been installed to the
horizontal
Tower Module on the Tower trailer,
lift the Tower to the FIRST
STAGE
. FIRST STAGE is a partially raised position that allows the remainder of
the full Access Platforms to be installed. After the remaining Access Platform(s)
have been installed, tighten the Platform and Arms.
IMPORTANT!
DO NOT TIGHTEN Walkway Arms until all Floor Sections are connected to
make a complete Walkway. DO NOT tighten the Handrails or Upright Posts.
On the ME1000S through
1600S Models, the Tower
Module and Roof Module
are shipped pre-
assembled together and
as one unit on the Tower
trailer. Some Eave
Platform assembly can
be done while the lift
truck is in First Stage lift.
Remaining Ladder-and-
Cage, and Partial Walkway
installations are done after
the Tower and Modules are
raised to vertical.
WARNING!
Use CAUTION when raising the Tower
section to First Stage. Be sure to use all
locking pins specified. Use CAUTION
when raising the Tower section to full
height. Stand clear! Follow all SAFETY
Decals. DO NOT attempt to MOVE the
truck with the hoist/Tower in a raised
position! Protect or LOCK THE
CONTROLS so that no hoist movement
can be made unintentionally. Failure to
follow this instruction could cause death,
serious injury, and/or equipment damage.
Figure 21.
Install Walkways at Tower Trailer FIRST STAGE Lift