Installation
Lenox
®
Lockers (includes Cubby & "Z" Lockers)
Bradley •
LK-INSTR-001 Rev. N; ECN 17-13-005
10/19/2017
7
Figure 3
DRILL 3/16" DIA .
PILOT HOLE IN
CONCRETE OR
BLOCK WALL
FILLER
DRILL 9/32" DIA .
CLEARANCE HOLE
THROUGH BACK
OF LOCKER
CENTERLINE
OF LOCKER
BACK
Locker Installation
3
Refer to your submittal layouts for proper locker position. The first locker is usually installed at a corner or at
the end of a run.
NOTICE! Make sure each locker is square AND level before securing into place (the lockers may be square but not
level so be sure to check both). Use shims as needed.
1 . Position the first locker according to your submittal layouts . Square and plumb the locker using shims as
required . Secure the locker to the wall in two places with the two 1/4" x 1-3/4" Lg . Tapcon screws . With the
screws centered across the width of the locker, place one near the top and one near the bottom as shown in
Figure 3 .
2 . Position the second locker next to the first locker . STANDARD LOCKERS ONLY: Square and plumb the locker
using shims (as required) to align the tops and fronts .
NOTICE! Lockers must be installed flush with adjacent lockers.
3 . Temporarily clamp the lockers together at the top and bottom . Drill four 9/32" clearance holes through locker
as shown in Figure 3 . The holes should be located 1-1/2" from the front of the locker and evenly spaced, top to
bottom . Fasten lockers to each other using the #10-24 male and #10-24 x 3/4" female sex bolts provided .
4 . Position additional lockers according to your submittal layouts . Square and plumb each locker using shims as
required . Fasten lockers to each other using the #10-24 male and #10-24 x 3/4" female sex bolts provided .
5 . Secure each locker to the wall in two places with the appropriate wall installation hardware provided . Use two
1/4" x 1-3/4" Lg . Tapcon screws, placing one near the top and one near the bottom of the locker as shown in