Install Guide - SleekWall
STEP-BY-STEP
GUIDE
IN-GROUND POST
INSTALLATION
STEP 2 (A)
-
POST SETUP AND ALIGNMENT
Working to a string line on the face of the post, insert the first post into the hole and gradually pour in
the concrete. Continually check the post alignment with a spirit level as the concrete is being poured.
Avoid using quick
setting concrete as it
can be corrosive to
aluminium posts
!
IMPORTANT
Allow 75mm min from
edge of post to edge of
ground
Slop top of
concrete away
from post (to drain
away water)
Set String Line approx.
5mm of post
Your string line should have a small amount of
clearance between it and your post. If you have
your string line always touching the post you can
risk pushing it slightly every time and the result
will be an ‘arc’ in the line of the fence.