Pit Type Truck Scale Installation Manual

14

Bolted Mounting Plate Shown

with Load Cell Mount Assembly

Connecting Modules

With the first end module in place you can now lift the next adjoining module into place and attach using the 

mounting plates and splice plates. If the adjoining module is a center module, attach another set of 8-hole 

mounting plates to the end of the module farthest from the end wall you started at.

The module will be lowered onto the 8-hole upper receiver plate connected to the end module that was in

-

stalled first, and onto the dummy stands at the opposite end. 

Once lowered onto the first module’s 8-hole upper receiver plates you may insert the remaining four mount

-

ing bolts into the bottom flange of both main beams on that end of the module. You will then attach the splice 

plates by bolting them with 7/8” bolts through the web of the adjacent main beams of the connecting modules.

Lower the last module into place with the end that has the welded mounting plates located closest to the end 

wall, and the end with the mounting and splice plate holes mating with the connecting module.

The module will be lowered onto the 8-hole mounting plate connected to the adjacent module and onto the 

dummy stands at the opposite end. Install the remaining hardware in the mounting plates and then install the 

remaining splice plates between the last modules.

Take a measurement of the distance between the last module’s main beams and the pit’s end wall. This mea

-

surement should be 1-1/4”. Take this measurement from both main beams to the pit wall to ensure that the 

distance is the same and that the module is parallel with the end wall. The measurements should be within 1/8” 

of each other. If they are not, adjust the module by leveraging a pry bar between the module and end wall to 

achieve squareness. 

The end modules are shipped from the factory with the end bumpers and 3/8” thick backing plates installed. If 

additional bumper thickness is needed, additional 1/4” and 1/8” bumper shims are shipped loose and can be 

installed behind the poly block bumpers.

Bolted Splices Plate Shown

with Load Cell Mount Assembly

Содержание BTEK BS-FECD-P-CPD-M

Страница 1: ...BS FESD P CPR M BS FESD P CPD M BS FECD P CPR M BS FECD P CPD M Models Include ...

Страница 2: ...www B TEK com 2016 Pit Type Truck Scale Installation Manual 2 ...

Страница 3: ... 8 Locating Plate Page 11 Lifting Modules into Place Page 11 Connecting Modules Page 14 Order of Module Installation Page 15 Conduit Installation Page 16 Concrete Deck Scale Preparation Page 17 Adjusting the Checking Page 18 Replacing the Dummy Load Cell Stands Page 18 Aligning the Load Cells Page 20 Connecting the Grounding Cables Page 21 Load Cell Cable Wiring Page 21 Maintenance Page 24 Spare P...

Страница 4: ...ts and Measurements authority prior to installation to verify that the foundation meets all requirements including those of the National Institute of Standards and Technology NIST and spe cifically Handbook 44 Prior to installation it is the customer s responsibility to verify that the equipment meets the requirements of the application Do not begin installation if this is unknown It is the custom...

Страница 5: ... do not locate indicators in direct sunlight or in areas subject to extreme temperature changes as this may affect the accuracy of the weighing You have a copy of the scale and foundation drawings specific to this installation on site at the time of installation You have a copy of this manual on site at the time of installation The foundation concrete has had a full twenty eight day period for pro...

Страница 6: ...ortion of the approach shall insure 1 ease of vehicle access 2 ease for testing purposes and 3 drainage away from the scale The scale drawings provided meet part a of this requirement The site must be located to meet parts b and c The site should have adequate room for trucks to properly align with the platform before pulling on This is especially important if trucks must turn before driving onto ...

Страница 7: ... Institute Code Allow the concrete foundation time to cure before erecting the scale Insufficient curing time of concrete may result in damage to the structural integrity of the scale foundation Unload the shipping crate of scale components prior to unloading scale platform modules from the truck to verify you have everything included on the packing list Open all boxes for individual equipment pie...

Страница 8: ...d with a punch Foundation drawings 4 way lifting chains with of 15 20 lengths to each corner 100 measuring tape Chalk line Laser level and or transit Hydraulic jack s Dummy load cells Various size wrenches and sockets 13mm 9 16 3 4 1 1 8 1 5 16 and 1 7 8 Pry bars Hand tools for working with cables wires Level s Foundation Base Plate Layout Verify that the foundation dimensions are correct and accu...

Страница 9: ...cluded with scale 5 2016 Center Line Center Line Foundation Base Plate Center Marks Note that the foundation base plates will be a combination of basic plates and combination plates that have the checking assemblies included as shown below BASIC BASE PLATE COMBINATION BASE PLATE with SIDE CHECKING four per scale ...

Страница 10: ...Ring Lower Receiver Isolation Ring Upper Receiver Grounding Straps Shim Plates It is recommended to layout all foundation base plates prior to permanently anchoring to the foundation Set the foundation plates in place Do not secure the plates to the foundation at this time Ensure that the foundation base plates are all level with each other Shim plates for use on the top of the foun dation base pl...

Страница 11: ...s prior to lifting the modules into place The first module to be placed onto the foundation is an end module which should be placed directly after the end wall The four dummy mount assemblies should already be in place on the base plates located on the chalk line centers on the foundation Prior to lifting the end module attach two 8 hole mounting plates to the end of the module closest to the cent...

Страница 12: ...alling the weighbridge mod ule onto the dummy load cell stands ensure that safety supports such as wood blocking is placed under the weighbridge module being lifted Lift the end module with the 8 hole upper receiver plate already bolted in place over the four dummy cell stand assemblies and slowly lower the module so that the button on top of each dummy stand is inserted into the thru hole located...

Страница 13: ... from both main beams to the pit wall to ensure that the distance is the same and that the module is parallel with the end wall The measurements should be within 1 8 of each other If they are not adjust the module by leveraging a pry bar between the module and end wall to achieve squareness The end modules are shipped from the factory with the end bumpers and 3 8 thick backing plates installed If ...

Страница 14: ...end that has the welded mounting plates located closest to the end wall and the end with the mounting and splice plate holes mating with the connecting module The module will be lowered onto the 8 hole mounting plate connected to the adjacent module and onto the dummy stands at the opposite end Install the remaining hardware in the mounting plates and then install the remaining splice plates betwe...

Страница 15: ...ype modules 1 Module starting at end wall location 2 Module resting on mounting plate of first module and subsequent modules will rest on second module s mounting plates 3 Last module rest on previous module s mounting plate welded mounting plate next to the end wall 4 cell module starting at end wall location ...

Страница 16: ...scale for a concrete deck pour The conduit is shipped loose in 10 lengths Conduit must be cut to length in the field as needed for the scale s length and width Enough conduit is supplied for the scale length and width at each load cell location Conduit clamps are included as well with larger beam clamps for connecting to main beams and slightly smaller clamps for connecting to crossmembers Three c...

Страница 17: ...s a temporary crossmember under the sheeting You will need to notch the two top corners to avoid interference with the radii between the top flange and web Cut two additional pieces of lumber to support both ends of the crossmember These pieces will fit between the bottom of the wooden crossmember support and the top side of the bottom flange of the main beams This distance may vary Take a measure...

Страница 18: ... adjusted to minimize the lateral movement of the weighbridges when replacing the stands Prior to lifting a module weighbridge place safety blocking under one of the main weighbridge structural beams with approximately 1 2 gap between the block and bottom of the beam This will stop the module from falling to the foundation in the case of a stand or load cell falling over Starting with a load cell ...

Страница 19: ...te amount of grease on the top button of the load cell bottom cup Slide the foam ring over the top of the load cell bottom cup aligning with the antirotation pin that is protruding Place the load cell onto the assembly taking care that thenotch in the bottom of the load cell aligns with the anti rota tion pin The cable connector on the load cell should face the center of the scale towards the cond...

Страница 20: ...is aligned both horizontally and vertically by ensuring that the air bubble is visible between marked lines If the load cell is out of level adjustments can be made by realigning the foundation base plate Repeat the check with the level to verify that the load cell is aligned correctly Continue to readjust the locating plate as needed B TEK Load Cell Surface Level Once the entire scale has had the...

Страница 21: ... diagram on the following pages Additionally a wiring diagram was included with your scale package along with the foundation drawing It is important that all cables be installed so that they do not touch the ground and are internal to the scale Zip tie all excess cable and attach to hangers near the junction box Your digital Pit Style scale package will include all load cell cables junction box es...

Страница 22: ...www B TEK com 2016 Pit Type Truck Scale Installation Manual 22 See larger drawing in packet ...

Страница 23: ...2016 www B TEK com Pit Type Truck Scale Installation Manual 23 See larger drawing in packet ...

Страница 24: ... lock washer HW B 1 4 20X1 1 4 20 X 1 L hex bolt J box mounting bolt HW N 1 4 20H 1 4 20 hex nut J Box mounting nut HW W 1 4L 1 4 lock washer J box mounting washer HW W 1 4F 1 4 flat washer J box mounting washer HW B 5 16 18X 75 5 16 18 X 3 4 L hex bolt Buss bar bolt HW N 5 16 18H 5 16 18 hex nut Buss bar nut HW B 5 8 11X2CSCS 5 8 11 X 2 L socket counter head cap screw Deck plate mounting bolt HW ...

Страница 25: ...up Load cell mount assembly 899 100021 75K 100K foam debris ring Load cell mount assembly 899 100025 M6 X 30 anti rotation pin Load cell mount assembly 899 100022 75K Lower receiver mount Load cell mount assembly 899 100043 100K Lower receiver mount Load cell mount assembly 899 100023 75K Isolation disc Load cell mount assembly 899 100039 100K Isolation disc Load cell mount assembly 100 61071 Shim...

Страница 26: ...B TEK Scales LLC 1510 Metric Ave SW Canton Ohio 44706 800 266 8900 Direct 330 417 8900 Fax 330 471 8909 Monday Friday 7 00 AM 5 00 PM www B TEK com sales b tek com ...

Отзывы: