Section 2: Installation
2.7
Commissioning
NOTICE
Check that values of electrical supply to the control group (if foreseen) are compatible
with those on the plate on the junction box (Figure 17).
!
WARNING
Installation, commissioning and maintenance and repair works should be made by
qualified staff.
Upon actuator commissioning please carry out the following checks:
•
Check that the values of pneumatic supply available in the system are compatible
with those reported on the identification plate of the actuator (Figure 1).
•
Check that electrical values of supply to the control group comply with the ones
reported on junction box (Figure 17).
•
Check the absence of leakages in the hydraulic connections.
•
Check that paint is not be damaged during transport, if necessary repair the
damages to paint coat.
•
Carry out all kinds of operations and check their proper execution (Section 3.3).
•
Check the absence of leakages in pneumatic connections.
•
Check proper operation of all the due signalling.
•
Check oil level in gas-hydraulic tanks (Section 5.1.1).