Check the chimney pot / terminal and general condition of the
brickwork or masonry. If the chimney or flue is in poor condition or if
there is no up-draught do not proceed with the installation. If there is a
history of down-draught conditions with the chimney / flue, a tested and
certificated flue terminal or cowl suitable for the relevant flue type should
be considered.
6.
A spillage test must always be carried out during commissioning of
the appliance.
1.6
FIRE PLACE OPENING AND CHIMNEY CATCHMENT SPACE
The front opening of the fire place must be a minimum of 560mm wide, and
690mm minimum in height. If the opening exceeds these dimensions then a
surround must be constructed from suitable non-combustible material to produce a
correct size opening. Any surround must be suitably sealed to the fire place to
prevent leakage. See below in fig.1
When installing into a brick built chimney, you must ensure that there is sufficient
depth to accomodate any debris which may fall from the chimney. This depth
must be sufficient to accomodate 12 litres of volumetric space.
Fire Opening
560mm Minimum
730mm
Minimum
600mm Minimum
Fig. 1
690mm Minimum
Minimum Flat
Sealing Area
6