WWW.BALTIMOREAIRCOIL.COM
28
NOTE:
Not all units receive a
mid-support.
Detail C
PEK
Figure 42.
Fill Access Platform with Side Ladder – PFi-0709,
1012, 2012, 1212, 2412
Detail B
Toe board
PHA
Detail A
Platform frame
Detail D
PHA
PHK
(PHL other end)
2. Lift the platform module into place and secure the platform frame to the factory
installed brackets on the casing frame. For 18’ long units, use the 5/16” hardware
provided to secure the platform frame to the center supports. See
Figures 43
and
44
,
Detail G
. For all units, use the 1/2” x 1 1/4” bolts provided to secure the platform
frame to the end supports. See
Figures 41
to
44
,
Detail B
.
3. Secure the support channels PHA to the platform frame using the 1/2” x 1 1/4” bolts
provided. See
Figures 41
to
44
,
Detail C
.
4. Secure the support channels PHA to the basin at the end locations using the adapter
brackets PHK and PHL. See
Figures 41
to
44, Detail D.