PFi Closed Circuit Cooling Towers and PCC Evaporative
Condensers should be rigged and assembled as outlined
in this manual.
These procedures should be thoroughly reviewed prior to the
actual rigging and assembly of the equipment to acquaint
all personnel with procedures to be followed and to ensure
that all necessary equipment will be available beforehand.
If outstanding circumstances require a departure from the
procedures outlined in this manual, contact your local BAC
Representative for guidance.
Be sure to have a copy of the submittal drawings available for reference.
If you do not have a copy of these drawings, or if you need additional
information about this unit, contact your local BAC Representative whose
name and telephone number are on the outside of the cold water basin. The
model number and serial number of the unit are also located in this area.
Some parts that ship loose are labeled with unique three key codes for
identification purposes. These three key codes are referenced throughout this
guide to identify parts to be assembled in the field.