RELEASE DATE
7-11-14
REFERENCE
NUMBER
INS-1330.2
40429 Brickyard Drive • Madera, CA 93636 • USA
559.438.5800 • FAX 559.438.5900
www.bklighting.com • [email protected]
B-K LIGHTING
on bottom
drill through sides
1. Connect branch conduit connectors (By Others)
to the junction box using either the threaded
conduit entries on the bottom of the junction
box or through holes drilled into the sides of
the junction box.
Do not remove the yellow temporary cover
or foam spacer during rough-in.
2. Place housing in hole. Align junction box in the
path of the conduit trench.
3. Insert (4) pieces of ½” EMT conduit through the
Stability Flange™. Hammer into substrate until
secure.
Leave sufficient clearance to elevate housing
to finished grade.
Top of yellow temporary
cover level to
finished grade.
4. Raise housing on EMT to finished grade (top of
yellow temp cover). Use bubble level on yellow
temporary cover to aid in leveling housing.
5. When top of yellow temporary cover is level
with finished grade, tighten screws on Stability
Flange™ to secure housing to EMT. Remove
excess EMT as needed.
6. Connect the conduit to the conduit connectors.
Housing
TENAYA2® ICEE™ SERIES
Housing Installation
Soil Prep
A. Determine Soil Type by referencing DIG-IT
Guide. Prep soil according to DIG-IT Guide.
J-Box
Conduit
Trench
24”
Dia.
B. Determine Soil Type by referencing DIG-IT
Guide.
C. Dig hole 24” wide and 30-36” deep.
Conduit
Trench
Excavated
for Housing
D. Prep soil according to DIG-IT Guide.
IMPORTANT SAFETY INFORMATION LISTED ON REVERSE
READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS