Autometers Systems IC7-C Скачать руководство пользователя страница 7

7

Wiring Information

Power Supply

The standard IC7-C and IC9-C 
requires a 230 volt, 50Hz supply. 
This is provided from the L3 
phase and Neutral internally.

Wiring

Electrical and communication 
connections are made to 
terminals 1-6 at the lower half 
of the meter. Communication 
Modbus 485 connections are 
made via the two sockets at the 
top of the meter on the side. 
Please see diagram 3.

Programming the 
Meter

To program the meter the dill 
switch, number “8” on the lower 
dill switch block must be in the 
“on” position.

Programming the Modbus 
Meter Register

Each meter that is connected to 
a Local Area Network (LAN) must 
have a unique modbus register 
so that it can be identified by the 
computer processor. Allocating 
a meter modbus register is 
accomplished using the upper 
block of dill switches. The dill 
switches in this block each 
represent a number, in geometric 
progression starting with dill 
switch number “8”. Thus switch 
number “8” represents register 
number “1”, switch number “7” 
represents register number “2”, 
switch number “6” represents 
register number “4”, switch 
number “5” represents register 
number “8” and so on.  
To allocate a meter register 
number the required dill switches 
must be switched into the “on” 
(up) position. 

Thus:  To allocate meter register 
number “1”, only dill switch 
number “8” on the upper block 
of dill switches needs to be in the 
“on” position.
To allocate meter register number 
“14” dill switches numbers “5”, 
“6” and “7” must be in the “on” 
position.
To allocate meter register number 
“39” dill switches numbers “3”, 
“6”, “7” and “8” must be in the 
“on” position. Etc.

Programming the 
Meter Functions.

The operating functions of the 
meter, such as baud rate, data 
format etc are programmed using 
the lower block of dill switches, 
as follows:

Baud Rate

Programming the Baud rate 
utilises dill switches numbered 
“1” and “2” on the lower dill 
switch block, as follows:
Baud Rate  Dill Switch  Dill Switch
 

2

9600 

Off 

Off

19200 

On 

Off

38400 

Off 

On

1200 

On 

On

Wire Mode

Programming wire mode utilises 
switch number “3”, as follows:
Two wire mode: switch  Off
 Four wire mode: switch On

Modbus Type

Programming the modbus type 
utilises switch number “4”, as 
follows:
RTU:    switch  Off
ASCII:  switch  On

Parity Type

Programming the parity type 
utilises switch number “5”, as 
follows:
Even:  switch  Off
Odd:   switch  On

Data Format

Programming data type utilises 
switch number “6”, as follows:
ASCII string:     Off
Floating point:   On

Floating Point Format

Programming the floating point 
format utilises switch number 
“7”, as follows:
High word first:  switch Off
Low word first:   switch On

LED Mode

Programming the LED mode and 
CT ratio utilises switch number 
“8”, as follows:
Calibration 1000 impulses per 
Kwh: switch On                     
Kwh impulse with output relay:         
switch   Off

ON

DIP

1

2

3

4

5

6

7

8

1

2

3

4

5

6

7

8

TOP SWITCH

MODBUS
ADDRESS

ON

DIP

1

2

3

4

5

6

7

8

1

2

3

4

5

6

7

8

LOWER SWITCH

MODBUS
PARAMETERS

Содержание IC7-C

Страница 1: ...installation and operation manual IC7 C and IC9 C horizon r a n g e The fusion of land based metering and ether based monitoring 9...

Страница 2: ...ing Slide the back of the meter first through the opening on the rear side of the door and then push the bezel from the front side over the protruding clear plastic and push fully home until it locks...

Страница 3: ...t programming details for your chosen CT ratios e When the process is complete press the Function key to take you back to the default screen Note When setting CT ratios and if you have only three digi...

Страница 4: ...IMPORT ENERGY KWH 000000 00 KVAH 000000 00 KVARH 000000 00 EXPORT ENERGY KWH 000000 00 KVARH 000000 00 VOLTAGE L 1 000 0 L 1 L2 000 0 L2 000 0 L2 L3 000 0 L3 000 0 L3 L1 000 0 FREQUENCY 50 00Hz AMPS L...

Страница 5: ...will take you to the desired screen To return to the normal screen press FUNCTION key again If you enter an incorrect number or a function which is not available on this model you will see the screen...

Страница 6: ...50 To check connections enter function 50 See Page 5 function operation display Press Funct key to see connections Press Funct key to return to normal display PULSE TEST Function 60 To test the relay...

Страница 7: ...ches needs to be in the on position To allocate meter register number 14 dill switches numbers 5 6 and 7 must be in the on position To allocate meter register number 39 dill switches numbers 3 6 7 and...

Страница 8: ...se Duration 80 100 ms closure Pulse Value C T Value less than 1000 5A 1 kWh imp C T Value 1000 5A or more than 10 kWh imp 0 4 0 3 0 2 0 1 0 1 0 2 0 3 0 4 0 1 1 0 2 0 3 0 4 0 5 0 6 0 IC9 Load Curve 0 5...

Страница 9: ...n depth stock holding combine to provide a level of service which has earned the appreciation of customers across the spectrum of the UK and export markets Computerised distribution systems are geared...

Отзывы: