Operation 

The GSCM is powered by 12 to 24VDC from a battery 
bank and will start generators for 12 to 48V systems. 
For 48V systems the GSCM must be powered by a 24V 
or less tap on the 48V battery bank. Adjustment for 
the timing controls is done during the set–up period 
using three push button switches on the front of the 
GSCM unit. The up and down buttons allows the user 
to move back and forth through the different timing 
parameters, and change the value when in change 
mode. 
The change/ store buttons allows the user to change 
and then store the new setting. LEDs indicate which 
setting is being addressed and the stored value can be 
read on the test points. For example: a crank delay 
voltage setting of 2.5V is 50% of the 0 to 60 second 
timing range or 30 seconds (See Adjustment Chart).  
Timing values are stored in the memory regardless of 
power removal until changed. 
 
The GSCM comes factory pre-set: 

 

 

Crank delay is set at 5 seconds 

 

Maximum crank is set at 15 seconds 

 

Load transfer delay is set at 60 seconds 

 

Load pre-off delay is set at 90 seconds 

 

Battery cut-in voltage is set at 11.5V 

 

Battery cut-out voltage is set at 13.5V 

 

Run/crank disconnect is set at 30Hz 

 

Under and over speed shutdown is set at 0 

 

30 day exercise runtime is set at 0 (de-activated)   

 
The GSCM provides a 30 day exercise function which 
can be synchronized with a photo voltaic input to only 
start each 30 day period at the beginning of the solar 
charge day. A user supplied DC relay can be energized 
during the 30 day generator exercise to override a 
battery charger and allow the battery bank to equalize 
by charging the batteries above the normal charger 
cutoff point during the exercise period. 
 

Also, it will start and control 

gas, propane &                    

diesel driven pumps 

 

 

 

 

Specifications 

 

SIZE: 

5.5”L x 3.3”W x 1.5”H 

 

WEIGHT: 

20 Ounces 

 

MOUNTING:  

2 Screws through tabs 

 

POWER: 

12V to 30VDC 

                                       Quiescent current ˂ 10mA 
                                       Relay current ˂ 25mA each @ 12V 

 

CONNECTIONS: 

Qty. (29) 1/4” Spade terminals 

 

ON-OFF INPUTS: 

Grounded input = on condition 

 

Open input = off condition 

 

MANUAL INPUTS: 

Grounded input = on condition 

 

12-24V Outback signal = Start 

 

Open = off 

 

VOLTAGE INPUTS: 

0-60VDC 

 

FREQUENCY INPUTS:  120-300 VAC 0-100Hz 

 

ADJUSTMENTS:           Qty. (1) single turn potentiometer 
                                       (0-5VDC=adjustment range) 
        Crank Delay                           0 to 60 seconds 
        Maximum Crank                   0 to 60 seconds 
        Load Transfer Delay             0 to 60 seconds 
        Load Pre-Off                          0 to 120 seconds 
        Battery Charge                       
             Cut-In Voltage                  0 to 60VDC 
             Cut-Out Voltage               0 to 60VDC 
        Under Speed Shutdown      15 to 75 Hz 
        Over Speed Shutdown         15 to 75 Hz 
        Run/Crank disconnect          15 to 75 Hz 
        30 Day Exercise Runtime     0 to 1 hour  

 

OUTPUT RATINGS: 

Qty. (5) 10Amp 28VDC Relay Contacts 

 

Qty. (2) Open Collector NPN Transistors 

 

FAULT DETECTION: 

5 conditions that lock out generator 

 

MAX. RUNTIME: 

12 hours in automatic start 

 

AMBIENT TEMP: 

-30 to 70°C

 

Содержание A0217

Страница 1: ...Generator Start Control Module Part GSCM Rev C Code Version 5 13 ATKINSON ELECTRONICS INC 14 West Vine Street Murray Utah 84107 ...

Страница 2: ... not already running before trying to start a second or third time Features Applications Automatic starting load transfer and shutdown for gas and diesel generators Off grid generators Automatic adjustable voltage set points for generator battery charging applications 0 60VDC Works with 12 24 or 48V battery systems Provides fault shutdown for low oil pressure high temperature and under speed or ov...

Страница 3: ...e is set at 0 de activated The GSCM provides a 30 day exercise function which can be synchronized with a photo voltaic input to only start each 30 day period at the beginning of the solar charge day A user supplied DC relay can be energized during the 30 day generator exercise to override a battery charger and allow the battery bank to equalize by charging the batteries above the normal charger cu...

Страница 4: ...www atkinsonelectronics com Circuit Board Division 800 261 3602 4 Revised 09 18 GSCM Wiring Diagram ...

Страница 5: ...e maximum crank lockout condition This lockout condition remains until the GSCM is reset by momentarily shorting the reset terminals 7 and 8 together after which the start LED blinks for 60 seconds and then enters ready mode Powering down the GSCM for 5 seconds and powering it back up will also clear the maximum crank lockout condition with the GSCM returning to ready mode 6 When the generator sta...

Страница 6: ...ins 7 and 8 momentarily The open collector transistor terminal 18 will energize a user supplied DC relay not exceeding 180 milliamp coil current whenever a fault shutdown occurs and will de energize the relay when the fault is reset The shutdown conditions are as follows 1 Failure to start with 4 cranking attempts See GSCM STARTING SEQUENCE section 4 5 The max crank max runtime fault LED blinks ra...

Страница 7: ... will shut down the generator and indicate a maximum runtime fault by slowly blinking the max crank max runtime LED See GSCM SHUTDOWN CONDITIONS section 6 This runtime fault is only active in the automatic starting mode 6 The GSCM will clear the max runtime fault if the reset terminals 7 8 are momentarily shorted a manual start signal is applied to terminals 5 6 or a period of 12 hours passes from...

Страница 8: ...e to 0VDC store setting advance to high Hz position and set to zero volts both must be set 9 To re enable the 5 and 10 minute time delays the GSCM must enter adjustment mode as in paragraph 1 of this section and then the cut in and cut out adjustment re entered and stored without the jumper between terminals 15 and 16 Restoring the GSCM factory default values as described in GSCM Reset Conditions ...

Страница 9: ...ad transfer 0 120 Second Load Pre Off Blinking load disconnected cool down period before shutdown Battery Charge Cut In x12 Blinking battery voltage lower than cut in point during 5 minute delay Battery Charge Cut Out x12 Blinking battery voltage greater than cut out point during 10 minute delay 15 75Hz Under Hz Shutdown Blinking generator Hz under speed less than trip point during 10 second delay...

Страница 10: ...rank Delay 5 second minimum 60 seconds Maximum crank time Will not energize starter 60 seconds Load transfer delay Ignition and load relays energize together 60 seconds Load pre off delay Ignition and load relays de energize together 120 seconds Battery charge cut in Ignores automatic battery charge function Switched auto start Battery charge cut out Ignores automatic battery charge function Switc...

Страница 11: ...e generator has reached 30Hz or half speed If this setting doesn t allow the start input to remain engaged long enough for the generator to stay on line adjust the run disconnect setting to 55Hz See GSCM INITALIZATON AND ADJUSTMENT for changing adjustments The K4 shutdown relay provides a momentary stop signal until the generator AC Hz has dropped to zero The K3 ignition relay provides a continuou...

Страница 12: ...rations are shown for both automotive and magneto type with or without fuel valves High speed 3600 RPM generators may need the crank disconnect hertz adjustment set to 20Hz or less to avoid over driving the starter Low Speed Gas Propane Generator with Safeties The low speed gas propane generators also wire the same as in application 2 However the installer should determine ignition type and oil an...

Страница 13: ...ession solenoid furnished with the generator must be wired to K4 shutdown relay to energize on shutdown Automatic Generator Powered AC Pump In this application the GSCM is connected to a pressure or level switch into the battery sense terminals To make the appropriate cut in and cut out adjustments See AUTOMATIC STARTING FOR BATTERY CHARGING section 9 The cut in and cut out adjustments must be set...

Страница 14: ...a special low voltage generator frequency input version for 12V alternator applications GSCM 12V ALT 255 Hz See AUTOMATIC STARTING FOR BATTERY CHARGING section 9 4 9 Generator Powered Air Conditioner The room thermostat should be line voltage slow action type to minimize short cycling signals the generator to start The GSCM K5 load transfer relay starts the air conditioner after the generator is r...

Страница 15: ...ter the GSCM starts the generator with a 3 wire start stop or any other generator starting application to match the type of generator to be controlled If the user desires the voltage from the generator s battery may be connected to the GSCM on terminal 4 and the GSCM will start the generator automatically to charge its own battery when the voltage falls below the battery cut in threshold voltage T...

Страница 16: ...m the date of shipment by Atkinson Electronics Inc or its authorized distributors to the original Customer Atkinson Electronics Inc will repair or replace at our option any defective products provided that our inspection discloses that such defects developed under normal and proper use This warranty does not extend to goods subjected to misuse neglect accident or improper installation or to mainte...

Отзывы: