5.2
ELECTRICAL INSTALLATION, cont.
INPUT WIRING MUST BE PERFORMED BY A QUALIFIED ELECTRICIAN
FAMILIAR
WITH
STANDARD
SAFEGUARDS
AND
PROCEDURES
REQUIRED BY THE INSTALLATION OF THIS TYPE OF EQUIPMENT.
POWER MUST BE REMOVED FROM THE INPUT DISTRIBUTION SYSTEMS
SUPPLYING POWER TO THE AC15QTP OR AC20QTP PRIOR TO THE
START OF THE FOLLOWING STEPS. INPUT POWER MUST BE SECURED
(LOCKED) IN THE OFF (DE-ENERGIZED) STATE UNTIL INSTRUCTED
OTHERWISE BY THIS DOCUMENT. ALSO SECURE IN THE OFF STATE
ANY CIRCUIT BREAKER(S) IN THE SWITCHGEAR PANEL THAT MAY BE
SUPPLYING SHIP’S BUS POWER TO THE CONVERTER OUTPUT
TERMINAL BLOCK. FAILURE TO FOLLOW THESE PROCEDURES CAN
RESULT IN DAMAGE TO THE EQUIPMENT, AND CAN PRESENT THE RISK
OF INJURY OR DEATH TO THE INSTALLER OR THE OPERATOR.
5.2.1 Input Power Connections
The converter is supplied with compression type terminal blocks for input power connections
(SHORE POWER). These terminal blocks accept wires in the range of 8 to 2/0 AWG. Refer to
the applicable class standard for selection of required wire gauge and type. Please refer to Figure
4 for more information.
If only a single shore power input is to be used, it must be connected the SHORE POWER 1
INPUT terminal block. The SHORE POWER 1 and SHORE POWER 2 inputs are fully isolated
and have no phase orientation requirements if dual shore power inputs are used.