AC15QTP And AC20QTP Operations Manual....
13
5
INSTALLATION
The installation section is divided into two parts: the first will cover mechanical installation, the
second, electrical installation.
Read this manual thoroughly prior to attempting the installation. Improper installation is the
most significant cause of system start-up problems and service issues over the product’s life.
Upon receipt of the equipment, perform an external visual inspection. Verify that nameplate
information is consistent with the ship’s power requirements (required form, voltage, and
frequency).
Proper planning will speed up installation, location, and connection of the equipment. Follow
the suggested minimum clearances provided in Table 2.
Ensure the room/compartment has adequate ventilation and cooling. The thermal load
presented by AC15QTP will be approximately 6,650 BTU/Hr at maximum continuous load,
and the AC20QTP will be approximately 8,670 BTU/Hr at maximum continuous load.
THE CONVERTERS WEIGH UP TO 340lbs. (154kg) DEPENDING UPON
MODEL AND INSTALLED OPTIONS. EXTREME CAUTION MUST BE
EXERCISED IN HANDLING AND INSTALLATION TO AVOID EQUIPMENT
DAMAGE OR INJURY TO PERSONNEL. AN ADEQUATE MATERIAL
HANDLING DEVICE SHOULD BE USED FOR UNLOADING, MOVING, AND
POSITIONING THE SYSTEM.