Chapter 4: Powering the Modular Switch
Cabling the DC Power Supply
Quick Start Guide: 7300 Series Modular Data Center Switches
23
Step 2
Remove the Flange locking nuts from each of the terminal studs.
Figure 4-6: Remove the Flange locking nuts from each terminal stud
Step 3
Secure each power cable lug to the terminal studs with the Flange locking nuts.
•
Attach the positive (+) DC source power cable lug to the RTN (return) terminal.
•
Attach the negative (–) DC source power cable lug to the –48V (input) terminal.
•
Torque the two Flange locking nuts to 5.1 N•m (45 in. lbs.).
Figure 4-7: Attaching the cables to the terminal studs
Figure 4-8: Securing the cable lugs to the terminal studs with the Flange nuts
Содержание DCS-7304
Страница 10: ...6 Quick Start Guide 7300 Series Modular Data Center Switches Specifications Chapter 1 Overview ...
Страница 48: ...44 Quick Start Guide 7300 Series Modular Data Center Switches Two Post Rack Mount Parts Appendix C Parts List ...
Страница 52: ...48 Quick Start Guide 7300 Series Modular Data Center Switches Appendix D Front Panels ...
Страница 55: ...Appendix E Rear Panels Quick Start Guide 7300 Series Modular Data Center Switches 51 DCS 7316 Rear Panel ...
Страница 56: ...52 Quick Start Guide 7300 Series Modular Data Center Switches Appendix E Rear Panels ...
Страница 58: ...54 Quick Start Guide 7300 Series Modular Data Center Switches Appendix F Line Cards DCS 7320X 32C LC ...