12. If you are using the BOUT signal and have configured it to send light information, verify that it
is activated.
13. Press the SET
SET push button to reset all indications and latches.
14. If you are using the BI2 binary input as the master trip, activate it and verify that the trip has
occurred by repeating the steps 4 and 5.
15. Press the SET
SET push button to reset all indications and latches.
16. Repeat the steps 1 through 15 for all sensors.
9.3. Testing the unit operation time
An operation time test is not required at commissioning as it is performed by the manufacturer both as
a type test and as a routine production test. If you want to have more information of these tests, please
refer to the routine test reports sent with the AQ-103(LV) unit and/or consult your nearest Arcteq
representative for the type test reports.
However, if it is deemed necessary, you can conduct an on-site timing test with the following
instructions.
1. Use a calibrated relay test set.
2. Connect one of the test set's outputs to a camera flash (Canon xx or equivalent) to initialize
the flash and to configure the set's timer to start simultaneously with the flash.
3. Connect one of the AQ-110 unit's trip outputs (T1, T2, T3, T4) or high-speed outputs
(HSO [HSO1] ja HST [HSO2]) to a test set input and configure the input to stop the timer.
4. Place the camera flash within 20 cm (12 inches) of the sensor.
5. Initiate the flash and the timer by using the test set output.
6. Read the measured time between the simulated arc light and the operation of the trip
contact.
7. Subtract the digital input delay of the test set from the final measured time (if applicable). For
specific test instructions, please consult the manufacturer of the relay test set.
9.4. Test plan example