Configuring the Control Valve for No Hard Water Bypass Operation
No Hard Water Bypass equipment is sold separately. Only use no hard water bypass
valves supplied by the manufacturer of this product which are specifically design for use
with this valve. Select nHbP for control operation. For no hard water bypass operation, the
three wire connector is not used.
Selection requires that a connection to the No Hard Water Bypass Valve is made to the two pin connector labeled
ALTERNATOR DRIVE located on the printed circuit board.
Note: If the control valve enters into an error state during regeneration mode, the no hard water bypass will remain in its current state
until the error is corrected and reset.
Configuring the Control Vale for Separate Source Operation
Select SEPS for control operation. For separate source operation the three wire connector
is not used.
Selection requires that a connection to a Motorized Alternator Valve (MAV) is made to the two pin connector labeled
ALTERNATOR DRIVE located on the printed circuit board. The C port of the MAV must be connected to the valve inlet
and the A port connected to the separate source used during regeneration. The B port must be connected to the feed
water supply.
When set to SEPS the MAV will be driven closed before the first regeneration cycle, and be driven open after the last
regeneration cycle.
Note: If the control valve enters into an error state during regeneration mode, the MAV will remain in its current state until the error is
corrected and reset.
Configuring the Control Valve for Use of an Outside Signal to Initiate Regeneration
Select the desired option in step 7CS.
Selection only matters if a connection is made to the two pin connector labeled DP SWITCH located on the printed circuit
board. Following is an explanation of the options:
oFF
– Feature not used.
on0
– If the dP switch is closed for an accumulative time of 2 minutes an immediate regeneration will be signaled
to the unit.
dELy
– If the dP switch is closed a regeneration will occur at the scheduled delayed regeneration time of day.
HoLd
– If the dP switch is closed a regeneration will be prevented from occurring while there is a switch closure.