Anderson Group
Double Stretcher – Operator’s Manual
15
3
Settings and Start-up
This chapter describes the stages of preparation and the start up of the double stretcher
system of the 780SB wrapper.
Warning!
Please make sure to also follow the setup stages
described in the wrapper operator manual.
3.1
Before you start
Before operating your double stretcher, be sure that it is well greased and the rollers and the
folding arm are clean and have no defects (scratches).
3.2
Moving the wrapper
If needed, move your wrapper to the place you will be storing your bales.
Warning!
Before you move the wrapper for any reason be
sure that the double stretcher is locked in its
transport position. (section
Erreur ! Source du renvoi
introuvable.
on page 31).
3.3
Positioning of the double stretcher for wrapping
Before beginning the wrapping of bales, place the double stretcher in the wrapping position by
proceeding as follows:
1.
Remove the pin that holds the double stretcher arm in transport position.
2.
Unlock the arm of the double stretcher and put it in the wrapping position. The
angle of the arm should be less than 90° to the front of the wrapper.
3.
Insert the pin into one of the holes for adjustment of the arm to hold it in place while
wrapping.
NOTE :
The fixing point on the arm of the double stretcher
contains several holes which allow you to adjust for bales
of different dimensions. When you have adjusted the arm
to work for the type of bale you are wrapping, note which
hole you are using.