1
2
3
4
5
3/4" TOP SPUD
3
INSTALL VACUUM BREAKER TUBE
C
4
FLUSH OUT SUPPLY LINES
1
CLOCKWISE CLOSES
STOP VALVE
COUNTER-CLOCKWISE
OPENS STOP VALVE
REMOVE COVER
2
2
B
1.
Remove STOP VALVE COVER (
1
) from STOP
VALVE (
2
).
2.
Open STOP VALVE (
2
) with a flat blade screwdriver.
3.
Turn on water supply to flush line of any debris or
sediment.
4.
Close STOP VALVE (
2
) and replace STOP VALVE
COVER (
1
).
1.
Place the SPUD FLANGE (
1
) over the spud on
the Fixture.
2.
Place FRICTION WASHER (
3
) and SEAL WASHER
(
4
) inside SPUD COUPLING NUT (
2
) and thread
onto Spud. Do not tighten fully.
3.
Insert the VACUUM BREAKER TUBE (
5
) into the
SPUD COUPLING NUT (
2
) and push it down.
Note: If cutting VACUUM BREAKER TUBE (5) to size,
note that Critical Line (C/L) on Vacuum Breaker must
typically be 6” (152mm) above fixture. Consult Code
for details.