Page
27
of
38
Pre-Start Checks
󠇠
Heat pump unit is installed on level concrete with rubber
mounting blocks with adequate air flow around the unit
󠇠
Condensate drain located on the rear of the heat pump
unit can run to waste freely
󠇠
There are no flammable or dangerous materials
anywhere near or within the surrounds of the heat pump
unit
󠇠
Electrical main supply cabling is sized correctly
󠇠
Electrical main circuit breaker protection is correct rating
to suit the heat pump unit specifications
󠇠
Electrical supply, voltage and earthing checked
prior
to
start-up of heat pump unit, check electrical wires for
correct tension
Buffer tank temperature probe installed in buffer tank
sensor well with heat transfer paste
Buffer tank temperature probe to hydronic supply/flow
water line if buffer tank is not used
󠇠
Hot water tank temperature probe installed in hot water
storage tank sensor well with heat transfer paste if
applicable
󠇠
External thermostat/control wiring installed correctly
(No voltage to be applied to digital input terminals on
heat pump units)
󠇠
Water shut off valves installed on unit
󠇠
Pressure limiting cold water inlet valves installed with
correct back flow prevention
󠇠
Propylene glycol added to lower freezing point of
hydronic circulation water in low ambient conditions and
cooling applications
For cooling applications -10 glycol freezing level is
recommended
󠇠
Spring check valves installed in hydronic and hot water
flow lines on all reverse cycle combination heat pump
unit/systems
Содержание ASHP-23
Страница 6: ...Page 6 of 38 Diagram Photo Copyright AusGeothermal 2018 ...
Страница 7: ...Page 7 of 38 Commercial Hot Water ...
Страница 8: ...Page 8 of 38 Hydronic Heating ...
Страница 9: ...Page 9 of 38 Hydronic Heating ...
Страница 10: ...Page 10 of 38 Hydronic Heating ...
Страница 11: ...Page 11 of 38 Swimming Pool Heating ...
Страница 20: ...Page 20 of 38 Diagram Photo Copyright AusGeothermal 2018 Heat Pump Location and Mounting Schematic ...