![Alpha ESS ES-Alpha-Smile 5-10KWH-v2 Скачать руководство пользователя страница 87](http://html.mh-extra.com/html/alpha-ess/es-alpha-smile-5-10kwh-v2/es-alpha-smile-5-10kwh-v2_installation-operation-and-maintenance-manual_2905569087.webp)
COMMISSIONING
85
Step2
Step3
Check the running status of the system in “Step 3”.
If the operation is normal as described in “Step3”, please remember to deactivate
the “Charging/Discharging Setting” by clicking “OFF” and save the changes.
Select “
ON
” to Charge Batteries from Grid”
please set the “Charging period 1” for the time and the SOC
would be
100
under this operation.
The relative value should be like this:Load = PV
±
GRID
–
Battery
Battery should be in
charging
status.
PV arrow
should be as
the picture shows.
±
:
>>
absorbing from grid: +;
<<
feed-in to
grid:-
If not correct, please check the CT or meter installed direction
of both grid and PV side
Содержание ES-Alpha-Smile 5-10KWH-v2
Страница 1: ...V01 INSTALLATION OPERATION MAINTENANCE MANUAL OF SMILE5 ENERGY STORAGE SYSTEM ESS ...
Страница 2: ......
Страница 68: ...Installer Account Register and Install New System 66 7 1 3 Overview of Functions for Installer Account ...
Страница 111: ...Appendix 1 System Overview 109 13 Appendix 1 System Overview ...
Страница 113: ...Appendix 2 Regional Application Standard 111 ...