Commissioning Procedure
PRE COMMISSIONING CHECKLIST (CONT..)
•
Check capacity control timing as detailed previously.
new
•
Check that each circuit trips on low pressure. The alarm should appear within
3 minutes.
new
•
The alarm will be recognised at the display circuit trip, clear the alarms as detailed
in the microprocessor manual.
new
RECORD
•
Reduce the flow rate to 75% of design and ensure that the evaporator pressure
differential switch or flow switch trips off this flow rate, adjust if necessary.
new
•
Ensure this alarm is recognised at the display and disengages the circuits operation
immediately. Restore flow rate to the design and check the alarm has self-cleared.
new
•
Turn the unit OFF by setting SWITCH 1, enable unit to the OFF position.
new
•
Fully open all liquid line and discharge service ball valves on each circuit.
new
Re-instate both the liquid injection and liquid line solenoid valves.
new
CAUTION
Remove the link from the MCCB for the auxiliary alarm contact.