Absco Industries
Assembly Instruction Manual
ABSCO GABLE CARPORT
MODEL: GCPDN2
6.0mW x 6.0mD x 2.98mH
Model: GCPDN2
8/06/23
5
1.
Footings (Piers)
Prepare site and mark out
positions as per the engineering
drawings.
Dig footings then box surrounds
to form a level flat concrete
surface for fixing framework to.
TIP: *It is recommended that the
concrete should be boxed 100
mm above ground level to allow
for a future slab.
2.
Slab - optional
Prepare footings as noted in A.
Pour a perfectly level slab to
the dimensions specified in the
engineering drawings.
Alternatively you may prefer
the slab to finish flush with the
outside of the footings.
The slab will be 100 mm thick,
reinforced with F72 mesh, laid 30
mm from the top. 50 mm thick
sand bedding on a water proof
membrane
No edge thickening is required
apart from the footings as
detailed.
FOUNDATIONS
GROUND
F72 mesh with
30 mm of top
cover
waterproof
membrane
50 mm sand
bedding
SLAB
100
600
PAD FOOTING
600x600x600
600
100*
12mm
dynabolts
GROUND
Please refer to engineering drawings that specify overall footings layout, slab and post dimensions.