User’s guide VUBB
|
1ZSC000562-AAL en
WARNING
The transformer must never be energized with an
inoperable end-stop.
The tap-changer installation is now complete. Proceed
with testing the transformer.
3.8 Energizing
The tap-changer can now be energized and commissioned.
WARNING
Before any work is carried out on the tap-changer,
make sure that the transformer is disconnected and
that grounding is properly executed. Obtain a signed
certificate from the engineer in charge.
3.9 Putting into operation
Put the motor-drive mechanism into operation by following
the instructions given in the BUE and BUL installation and
commissioning guide.
Check the oil level one month after filling. It is usual
for the oil level of the oil conservator to decrease due
to gas absorption in the oil.