1) To prevent oxidation of contact surfaces of the off-load tap changer it has to be moved from

side to side a few times, at least once a year.

2) function of alarms and tripping contacts of thermometers.

Inspection Measurements

In addition to the above instructions the following inspection measurement may be carried out:

1. Insulation resistance of windings

HV Winding to Earth
LV Winding to Earth
HV Winding to LV Winding
Reading below 75 megaohms should be reported to the manufacturer.

2. Transformer ratio test

Approximately 220 volts or 400 volts should be supplied from an  isolating transformer via a
regulating  transformer to one winding of the High-Voltage side of the transformer to be tested. HV
and LV readings can be taken  by means of a general-purpose meter. The measurements must be
carried  between  each  phase. The transformation ratio calculated from the voltage reading must be
compared  to the ratio of the rated voltages and to the values from the test report. Due to inaccuracy
of  the  general-purpose  meter  a difference of a few percentages may be possible. It is advisable to
use a transformation ratio bridge for the measurement.

3. No-load current

A small voltage fed between each phase and the star point (in a star connected transformer) via an

isolating  and regulating transformers will result in the reading of a series connected ammeter being
only a ten of milliamperes.

With  the same voltage reading the current taken by other phases can be measured. The excitation

currents  of  different  phases  should  be approximately the same magnitude. In a damage phase the
current  can  rise to tens of amperes thus the regulating transformer has to be protected by a suitable
fuse.

4.

DC resistance of windings

A satisfactory large DC source and an accurate resistance bridge meter are needed for the

resistance  measurement.  When disconnecting the measuring current instrument dangerous voltage
can be induced. Therefore a skilled person must perform the measurement.

Opening/Resealing Sealed type Transformers

Sealed  type  transformers  must not be opened unnecessarily as this could cause the oil to come out or air
to go in depending on the temperature of the oil. This  results in disturbances of the normal pressure
variations causing increased stress on the tank due to under-pressure or over-pressures.

When  opening  the transformer, for example to replace a bushing, opening and resealing must be
performed according to these instructions.

Opening

1) If the temperature of the transformer oil is  higher than +20...25°C, approximately 5% of oil

must be drained through the drain valve to relieve the pressure.

2) If the temperature of the transformer oil is below +20  °C, no draining is needed as there is

under-pressure inside the tank.

3) Filling  plug  can  then  be opened. If necessary the oil level can be lowered by draining through the

drain  valve before carrying out the planned maintenance. (If the transformer is provided with an oil
level indicator, it also acts as the filling plug).

Resealing

Содержание SAHARA 1000

Страница 1: ...ipment ABB Electrical Industries Co Ltd Kingdom of Saudi Arabia ABB SAHARA Series Compact Substation OPERATING INSTRUCTIONS MODELS 24kV 36kV SAHARA 500 SAHARA MAX 1 SAHARA 1000 SAHARA MAX 2 SAHARA 1600 SAHARA 2000 SAHARA 3000 ...

Страница 2: ...cal Inspection 7 MAINTENANCE AND PERIODIC INSPECTION 7 Bolt Tightness 7 Inspection and Testing 7 Routine Field Testing 8 1 Insulation Resistance Test 8 2 Connection Test 9 3 Mechanical Operation 9 TRANSFORMER MAINTENANCE 9 Inspection during operation 9 Maintenance during operation 9 Inspection and Measures to be taken during downtime 9 Inspection of oil leaks and precautions to be taken 9 Inspecti...

Страница 3: ...rtance of care in Site selection and design embodying features that provide adequate ventilation protection and security and which have taken account of appropriate fire moisture and explosion hazards Jointing Earthing Selection and setting of electrical protection in primary and secondary against overload overvoltage and short circuit Carrying out regular inspection and electrical and mechanical ...

Страница 4: ...ion has not sustained any damage during transportation Immediately upon receipt of the Package Compact Substation examine them to determine if any damage or loss was sustained during transit If abuse or rough handling is evident file a damage claim with carrier and promptly notify the nearest ABB office ABB ELECTRICAL INDUSTRIES CO LTD is not responsible for damage of goods after delivery to the c...

Страница 5: ... LIFT OR MOVE A TRANSFORMER OR PACKAGE COMPACT SUBSTATION WITHOUT ADEQUATE EQUIPMENT AND PRECAUTIONS 2 TERMINALS ARE FOR ELECTRICAL LOADING ONLY 3 DO NOT MAKE ANY CONNECTIONS THAT ARE NOT AUTHORIZED BY THE NAMEPLATE OR CONNECTION DIAGRAMS 4 DO NOT ENERGIZE THE SUBSTATION WITHOUT PROPERLY MADE GROUND OR EARTH CONNECTIONS 5 DO NOT ATTEMPT TO CHANGE THE TAP SETTINGS WHILE THE TRANSFORMER IS ENERGIZED...

Страница 6: ...due stress on the terminals Conductors should be securely fastened in place and adequately supported with allowances for expansion and contraction FINAL INSPECTION PRIOR TO ENERGIZATION After the Package Compact Substation has been found to be in good condition and the protective equipment is operational the substation may be connected to the network However it is recommended that the transformer ...

Страница 7: ...awings and previous test records before starting activity Scrutinize maintenance instructions given for the equipment to be maintained Maintenance information is given in the Operation and Maintenance Manual for each type of equipment The main dangers of such process are Inaccessible lubrication points greased for life cannot be lubricated and may seize up Areas not lubricated may be subject to co...

Страница 8: ...estigated for possible contamination on the surfaces NOTE For individual circuit protective device s resistance readings load and line conductors should be disconnected If not disconnected the test measurements will also include the characteristics of the attached circuits A temperature and humidity reading are recommended and recorded during the testing period Insulation resistivity is markedly e...

Страница 9: ...ntenance measures can be carried out which can not normally be performed during operation Before starting maintenance work the transformer has to be disconnected from the network and earthed or grounded When the disconnector has been opened one has to see to that they stay open and before grounding or earthing one has to test that they are voltage free i e with a voltage tester Inspection of oil l...

Страница 10: ...ten of milliamperes With the same voltage reading the current taken by other phases can be measured The excitation currents of different phases should be approximately the same magnitude In a damage phase the current can rise to tens of amperes thus the regulating transformer has to be protected by a suitable fuse 4 DC resistance of windings A satisfactory large DC source and an accurate resistanc...

Страница 11: ...energy may be different for different fuse types as well as the selection tables and protection characteristics It is compulsory to use the same type of fuse links in all phases type rated current The disconnector cannot be closed before the fuse links are changed Note According to IEC Publication 282 1 all 3 fuse links should be replaced even if only 1 or 2 of the fuse links in the three phase sy...

Страница 12: ...uring periodic checks established the best fixed periods for maintenance work It is also advisable to refer to the following rules The circuit breakers that operate rarely or which remain closed or open for long periods must be activated once in a while to prevent a tendency to jam which might cause reductions in the closing or opening speed During service circuit breaker must be visually check fr...

Отзывы: