The CB should be closed and ready.
3.
If external control Off/On is connected, check that it works.
Set
Operation to ExternalCtrl and use that control to switch On and Off, and check the
state of the function.
7.7.2.3
Verifying the autorecloser for 3-phase operation function SMBRREC
M12400-91 v9
Select the test cases to be run according to what is applicable to the particular application. It
can be, for example, three-phase single-shot reclosing or two-shot reclosing. Below, a case
with three-phase single-shot reclosing is described.
1.
Set
Operation = On.
2.
If the autorecloser for 3-phase operation function SMBRREC is not to be operated, ensure
that the SMBRREC input is activated. If SMBRRECis to be included, ensure that it is
supplied with the appropriate AC quantities.
3.
Simulate CB closed position by closing switch SC to make the BR relay start.
4.
Simulate CBREADY by closing the switch SRY, and leave it closed.
5.
Inject AC quantities to give a trip to the BR and to the START input.
Observe and preferably record the operation. The BR relay shall trip and reclose (start).
After reclosing, the SRY switch can be opened for about 5s and then closed again.
The autoreclosing open time and the sequence should be checked, for example in the
event recording. Check also the operation indications (disturbance report) and the
operation counters on the local HMI under Main menu/Tests/Function status/
SMBRREC(79,0->1)/SMBRREC:1
Should the operation not be as expected, this should be investigated. It could be caused
by an inappropriate setting or missing condition such as CBREADY.
6.
Repeat the sequence by simulating a permanent fault.
Shortly after the reclosing shot, a new fault is applied. If a single-shot reclosing program
is selected, there shall be one reclosing operation and then blocking of SMBRREC for the
set Reclaim time.
Before a new reclosing sequence can be run, the CBREADY and CBPOS (CB closed) must
be set manually.
7.7.2.4
Checking the reclosing conditions
M12400-123 v4
When checking the influence of a releasing condition it is suggested to first run a sequence
with the condition fulfilled. When the condition signal is removed, and a new sequence is run, it
indicates that the result was due to the changed condition. In case of a blocking signal the
procedure should be similar. Start without the blocking or inhibit signal, and then run a
sequence with the blocking or inhibit signal added.
Checking the influence of the INHIBIT signal
M12400-129 v4
1.
Check that the autorecloser function SMBRREC is operative, for example, by making a
reclosing shot without the INHIBIT signal.
2.
Apply a fault and thereby a START signal. At the same time, or during the open time,
apply a signal to the input INHIBIT.
3.
Check that the reclosing sequence is interrupted and no reclosing takes place.
Check closing onto a fault
M12400-137 v4
1.
Check that the autorecloser function SMBRREC is operative, for example by making a
reclosing shot.
1MRK 505 293-UEN B
Section 7
Testing functionality
Breaker protection REQ650
87
Commissioning manual
© Copyright 2013 ABB. All rights reserved
Содержание REQ650 1.3 IEC
Страница 1: ...Relion 650 SERIES Breaker protection REQ650 Version 1 3 IEC Commissioning manual ...
Страница 2: ......
Страница 12: ...6 ...
Страница 20: ...14 ...
Страница 28: ...22 ...
Страница 40: ...34 ...
Страница 42: ...36 ...
Страница 116: ...110 ...
Страница 123: ...117 ...