![ABB Relion SAM600 Скачать руководство пользователя страница 39](http://html.mh-extra.com/html/abb/relion-sam600/relion-sam600_installation-manual_3045258039.webp)
Section 7
Checking installation
7.1
Identifying hardware and software version
GUID-7527A986-F827-4104-B0E9-C62B1B0EF706 v1
The information of hardware and software versions of the IED are available on the label
attached on the case of the IED. There are also module labels that can be used to identify the
different modules inside the IED (such as input-output cards and so on).
7.2
Checking mounting
GUID-50578D7B-23D4-45B0-BB10-D3108EEF9B97 v2
Check that all fixing screws are tight and that all cables are connected.
7.3
Checking the power supply
M11725-2 v6
Do not insert anything else to the female connector but the corresponding
male connector. Inserting anything else (such as a measurement probe) may
damage the female connector and prevent a proper electrical contact between
the printed circuit board and the external wiring connected to the screw
terminal block.
Check that the auxiliary supply voltage remains within the permissible input voltage range
under all operating conditions. Check that the polarity is correct before energizing the IED.
7.4
Energizing the IED
GUID-E40DE80C-8DA4-4E17-876C-4CC3CE706347 v4
Before connecting the auxiliary power, check that the terminal strip is wired and placed
correctly. Remove the protective film from the top side of the unit.
During IED start-up, you can observe the internal fail relay that should change state to ready
after around 1 minute.
In order to get the following information in SAM600-IO, the service kit is need.
For more information on service kit, refer
SAM600-IO Technical manual.
During IED start-up, you can observe the following sequence:
1.
The Green Ready LED starts to flash.
2.
The LCD lights up and starting... is displayed.
3.
The main menu is displayed. A final steady green Ready LED indicates a successful start-
up of the device.
If the self supervision of the IED detects a diagnostic error during the start-up process, the
green Ready LED flashes. Further information on the error may be visible on the local HMI
under Main menu/Diagnostics/IED status/General. Note down the displayed information as
reference when contacting ABB technical support.
1MRK 514 030-UEN B
Section 7
Checking installation
Switchgear control unit SAM600-IO
33
Installation manual
© Copyright 2017 ABB. All rights reserved