8.
Change the magnitude of the voltage and current for phase 1 to a value higher than the
set value
DU> and DI<.
9.
Check that the start output signals STDUL1 and STDIL1 and the general start signals
STDU or STDI are activated.
10. Check that the start output signals for the current and voltage phases 2 and 3 are
activated by changing the magnitude of the voltage and current for phases 2 and 3.
9.5.2.6
Completing the test
M1405-130 v5
continue to test another function or end the test by changing the
TESTMODE setting to Off.
Restore connections and settings to their original values, if they were changed for testing
purposes.
9.6
Control
SEMOD53560-1 v2
9.6.1
Synchrocheck, energizing check, and synchronizing SESRSYN
M2377-3 v12
This section contains instructions on how to test the synchrocheck, energizing check, and
synchronizing function SESRSYN for single arrangements.
Prepare the IED for verification of settings as outlined in section
in this chapter.
At commissioning and periodical checks, the functions shall be tested with the used settings.
To test a specific function, it might be necessary to change some setting parameters, for
example:
•
AutoEnerg = Off/DLLB/DBLL/Both
•
ManEnerg = Off
•
Operation = Off/On
•
Activation of the voltage selection function if applicable
The tests explained in the test procedures below describe the settings, which can be used as
references during testing before the final settings are specified. After testing, restore the
equipment to the normal or desired settings.
A secondary injection test set with the possibility to alter the phase angle and amplitude of
the voltage is needed. The test set must also be able to generate different frequencies on
different outputs.
The description below applies for a system with a nominal frequency of 50 Hz
but can be directly applicable to 60 Hz. SESRSYN can be set to use different
phases, phase to earth or phase to phase. Use the set voltages instead of what
is indicated below.
Figure
shows the general test connection principle, which can be used during testing. This
description describes the test of the version intended for one bay.
1MRK 505 385-UEN C
Section 9
Testing functionality by secondary injection
Breaker protection REQ650
79
Commissioning manual
© Copyright 2017 ABB. All rights reserved
Содержание RELION 650 SERIES
Страница 1: ...Relion 650 SERIES Breaker protection REQ650 Version 2 2 IEC Commissioning manual...
Страница 2: ......
Страница 20: ...14...
Страница 24: ...18...
Страница 32: ...26...
Страница 42: ...36...
Страница 48: ...42...
Страница 52: ...46...
Страница 64: ...58...
Страница 118: ...112...
Страница 126: ...120...
Страница 127: ...121...