13.2 Commissioning via Web User Interface
Commissioning could be carried out via wireless connection to the inverter’s Web User Interface. Initial setup
of the system must therefore be carried out via a tablet, notebook or smartphone with a wireless connection.
NOTE –
D
This inverter can be powered both with AC or DC sources. In case of DC source is used, make
sure that irradiation is stable and adequate for the inverter commissioning procedure to be completed.
• Close the DC disconnect switches
(19)
to supply the inverter with input voltage from the photovoltaic
generator or close the AC switch downstream of the inverter (and AC disconnect switch
(09)
for the -S2,
-SX2 wiring box version) to supply the inverter with AC grid voltage. In the pre-commissioning phase the
“Alarm” LED keeps quickly flashing, “Power” and “GFI” LEDs are OFF.
• Once powered, the inverter will automatically create a wireless network (approx. 60 seconds after
switching-on).
SN WLAN: SSSSSSSSSS
PN WLAN:
.V2P
VKA
53.1
Mac Address:
AA:BB:CC:DD:EE:FF
PK: 0000 - 0000 - 0000- 0000
SN WLAN: SSSSSSSSSS
SN Wiring Box: ZZZZZZZZZZ
Remove and apply on the plant documentation
MAC: AA:BB:CC:DD:EE:FF
H
I
• Enable the wireless connection on the device which is being used
for the board setup (tablet, smartphone or PC) and connect it
to the Access Point created by the inverter system: the name of
the wireless network created by the system that the connection
should be established with, will be: ABB-XX-XX-XX-XX-XX-XX
where “X” is a hex digit of the wireless MAC address
(H)
(MAC address
can be found on the “Communication Identification Label” placed on
the side of the inverter).
• When required enter the PRODUCT KEY
(I)
(printed on the
“Communication Identification label” and applied during the
commissioning phase to the plant documentation) as access point
password (Note that it’s required to digit also the dash “-” characters
of the Product Key in the password field).
• Open an internet browser (recommended browser: Chrome versions from v.55, Firefox versions from v.50)
and enter the pre-set IP address 192.168.117.1 to access the Web User Interface.
• Follow the step-by-step commissioning wizard to complete the commission of the inverter.
After the settings are confirmed, the inverter restarts.
ATTENTION –
A
From the moment the grid standard is selected, there will be 24 hours available to
make any changes to the grid standard; after this, the “Country Select” feature is blocked and you can
make further changes only by resetting the remaining-time timer.
READ THE MANUAL –
E
For further information regarding the commissioning procedure via Web
User Interface, please refer to the product manual.
After the wizard procedure is completed, the inverter changes the behaviour of the “Power” and “Alarm”
LEDs
(08)
, in relation of the input voltage value:
Input voltage
LED Status
Description
Vin < Vstart
Power = Flashing
Alarm = OFF
The input voltage is not sufficient to enable connection to the grid.
Vin > Vstart
Power = Flashing
Alarm = ON
The input voltage is sufficient to enable connection to the grid:
the inverter waits for the grid voltage to be present to make the
connection to the grid.
• Depending of the supply source used to complete the installation wizard steps, close the disconnect switch
of missing voltage sources: In case of missing AC source close the AC switch downstream of the inverter
(and AC disconnect switch
(09)
for the -S2, -SX2 wiring box version); In case of missing DC source close the
DC disconnect switches
(19)
.
• When the input voltage is sufficient to allow the connection to the grid, the inverter will check the grid
voltage, measure the isolation resistance of the photovoltaic field with respect to ground and performs
other auto-diagnostic checks. During the preliminary checks on the parallel connection with the grid, the
“Power” LED keeps flashing, the “Alarm” and “GFI” LEDs are OFF. The inverter will ONLY connect to the grid
if all parameters fall within the ranges foreseen by current regulations.
• If the outcome of the preliminary checks to grid synchronization are positive, the inverter connects and
starts to export power to the grid. The “Power” LED remains fixed on while the “Alarm” and “GFI” LEDs are
OFF.