4.2.2.1
Procedure
1.
Open the terminal block cover located
on the rear panel of the UPS.
2.
Remove the protective plates of the cable
entries (the bypass hole should remain closed
for safety purposes if it is not used)
3.
Connect the wires according to the illustrations in the subsections that follow according to your
configuration (11 or 31, single or dual input feed). Run the cables through the holes from the
bottom to the top installing also the cable glands provided with the UPS.
Note: If the UPS is used as a standalone UPS, JP1 and JP2 must be connected. If the UPSs are
used in parallel configuration, the jumper between JP1 and JP2 must be removed.
4.
Check that all wires have been properly connected.
5.
Close the terminal box with the protective
cover. This is very important to prevent
access to energized cables and
connectors.
6.
Install the output breakers between the output
terminal and the load. The breaker should have
a leakage current protective function according
to the UPS voltage and current ratings.
Protective plates
Cable gland
Cable outer diameter:18-25mm
Cable gland
Cable outer diameter:16-28mm