23/54
MegaFlex 1000 to 1600
UPS Installation Guide / REV-A
4.7 Inter cabinet connections
Note!
The “Power Section cabinet” and “In/Out Section cabinet” must be installed on levelled floor.
Be aware of the heavy weight of the UPS cabinets, pay attention when moving the UPS cabinet.
Take care not to damage the UPS cabinets when moving by forklift.
MegaFlex 1000 to 1600 Preparation for interconnection of UPS cabinets
MegaFlex 1000 to 1600 is delivered split into two cabinets, “Power Section cabinet” and “In/Out Section
cabinet” (cabinet with Control Panel).
Align them together with the “In/Out Section cabinet” on the right side (cabinet with Control Panel).
Pay attention, that no loose cables are trapped when pushing the cabinets together.
For “Power Section cabinet” proceed in the following way:
-
Remove the front protection panels “A and B”.
-
Remove the top panel “C”.
For “In/Out Section cabinet” proceed in the following way:
-
Open the doors “D”.
-
Open the Electronic Module “E”.
-
Remove the front protection panels “F”.
-
Remove the top panel “G”.
Fig. 4.7-1 MegaFlex 1000 to 1600 – Cabinets positioning and interconnection
Once the 2 cabinets have been positioned and the various operations described in Fig. 4.7 have been carried out,
you can proceed to the various interconnections described in Section 4.7.1, 4.7.2, 4.7.3 and 4.7.4.
Note!
Performed all the interconnection procedures, describe in Section 4.7.1, 4.7.2, 4.7.3 and 4.7.4, you
must reassemble all the protections previously removed.
Power Section cabinet
In/Out Section cabinet
MG F_UL_1000
-1600_S1_UPS
cabinets_01US
A
B
F
C
G
E
D
D
Bus bars interconnection
(see Section 4.7.2)
Junction metal
connection cabinets
(see Section 4.7.1)
Control cables connection
(see Section 4.7.3)
Lower closures
with air inlet grids
see Section 4.7.4)
Lower closures
with air inlet grids
see Section 4.7.4)
Module not available in the
MegaFlex 1000 - 1100 - 1200