7. Make sure that the site complies with the relevant usability standards, such as
ADA and DIN 18040:
a. Limit the curb heights.
b. Take into account the limited reach of a wheelchair user.
For usability standards specifications, refer to section
.
8. Make the site as safe as possible.
a. Make sure that the EVSE can be clearly seen and monitored.
b. Apply 24/7 security control.
c. Install sufficient lighting.
4.3
Make sure that the floor space for the EVSE and the
airflow around the EVSE is correct
1. Make sure that the floor spaces meet the requirements. Refer to section
2. Make sure that the air flow inlet and outlet cannot get blocked. Think of snow or
objects.
4.4
Prepare the foundation
4.4.1
Prepare the foundation - general procedure
1. Select the correct foundations, according to the ground conditions.
2. Prepare the foundation for the power cabinets.
Type
Procedure
Prefab concrete foundation
Refer to section
.
Custom foundation
Refer to section
3. Prepare the foundation for the charge posts.
Type
Procedure
Prefab concrete foundation
Refer to section
.
Custom foundation
Refer to section
4.4.2
Prepare a prefab concrete foundation for the power cabinet
Preliminary requirements
•
Prefab concrete foundation. Refer to section
.
Pre-installation
28
9AKK107992A6488-EN | 004