GAA330-M
EMISSION MONITORING SYSTEM | OI/GAA330-M-EN REV. C
51
Start-up and operation
Start-up
CAUTION
The analyzer system must stand in its operating position for about
24 hours prior to start-up.
Before activating the power supply check once again that the analyzer
system operating voltage is set to match the line voltage.
NOTE
Initial startup of the analyzer system should be performed by trained per-
sonnel of the manufacturer or the supplier. ABB recommends having the
startup done by ABB personnel.
Prior to start-up
•
Check analyzer system seal integrity.
Power supply activation
1
Make sure that all fuse switches are deactivated.
2
Turn on the analyzer system power supply with the main switch.
3
Activate the fuse switches of the individual modules one after the other.
Function check
The following events will occur after the power supply is turned on:
1
The three "Power", "Maint" and "Error" LEDs light up.
2
The different booting phases are displayed on the screen. Also, the
software version is displayed.
3
After a brief time, the screen switches to measurement mode.
4
The
STATUS MESSAGE
softkey appears on the screen. This indicates the
possibility of a temperature or flow problem during the warm-up phase.
By pressing the soft key, the user can recall the status message sum-
mary and view status message details.
Date and time check
A correct date and time setting is required for a proper operation of func-
tions such as automatic calibration and time / date logging of error mes-
sages.
1
Select the date / time menu item:
MENU
→
Configure
→
System
→
Date / Time
2
Check and, if necessary, correct the date and time.
The analyzer system is factory-set to the GMT+1 time zone.
Содержание GAA330-M
Страница 2: ......
Страница 43: ...GAA330 M EMISSION MONITORING SYSTEM OI GAA330 M EN REV C 43 ...
Страница 44: ...44 GAA330 M EMISSION MONITORING SYSTEM OI GAA330 M EN REV C ...
Страница 84: ...84 GAA330 M EMISSION MONITORING SYSTEM OI GAA330 M EN REV C Notes ...
Страница 85: ......