24
GAA610-M
ADVANCED EMISSION GAS MONITORING SYSTEM | OI/GAA610-M-EN REV. B
… 5 Preparation for Installation
Material required for installation
Note
The materials listed below are not included in the scope of
delivery of the device, and must be provided by the customer.
Gas sampling
Wall tube with mounting flange
DN 65, PN 6, facing type A to EN 1092-1.
Gas lines
Gas line
Material
Sample gas (unheated line)
PTFE pipe 4/6×1 mm
Sample gas outlet
PTFE pipe 4/6×1 mm
Ambient air / Zero (N
2
)
PTFE pipe 4/6×1 mm
Calibration gases 1, 2, 3
PTFE pipe 4/6×1 mm
Instrument air
Stainless steel pipe, 10 mm,
via tube fitting
Condensate collecting bottle
PVC tube 4/6×1 mm
Mounting material
Screws and nuts to mount the analyzer cabinet on the wall.
A suitable lifting device (crane, block and tackle, lifting truck,
etc.) and lifting gear are required for transport and installation
of the analyzer cabinet.
For details regarding the size of the screws and nuts see the
‘Layout Plan’ in the drawings set.
Cable specification
Note
All cables entering the system must comply with the
flammability class VW1, FT1 or EN60332-1-2/-2-2.
Power supply lines
Analyzer cabinet supply
• 230 V AC, 50 / 60 Hz, Single Phase NON-UPS
power supply; fuse (external) 25A
• Cable Entry: M25 Cable gland for customer
supply cable;
• Cable Type: 3×10 mm
2
• Grounding cable: > 6 mm
2
Connecting cables between analyzer cabinet and sample handling
components
Sample probe power supply • 230 V AC 50/60 Hz;
• Cable Entry: M20 Cable gland for customer
supply cable;
• Cable Type: 3×2.5 mm
2
Probe Heater Alarm Signal • Cable Entry: M20 Cable gland for customer
supply cable
• Cable Type: 2×0.75 mm
2
Back-purge Unit Solenoid
Valves (SOV1/SOV2)
• Cable Entry: M20 Cable gland for customer
supply cable
• Cable Type: 2×1.5 mm
2
Signal lines (Connection between CEMS cabinet and scrubber system)
Analogue Signals to DCS
(only, if hardwired
connection is required)
• Shielded cables for the analog outputs
(current outputs)
• Cable Entry: M25 Cable gland for customer
supply cable
• Cable Type: 6×1 mm
2
Digital Signals to DCS
(only, if hardwired
connection is required)
• Cable Entry: M20 Cable gland for customer
supply cable
• Cable Type: 2×1 mm
2
(System failure)
• Cable Type: 2×1 mm
2
(Maintenance)
• Cable Type: 2×1 mm
2
(Maintenance Request)
• Cable Type: 2×1 mm
2
(Measuring Range Feedback SO
2
)
Modbus Signal to DCS
Cable Entry: M20 Cable gland for customer supply
cable
Ethernet to DCS
Cable Entry: M20 Cable gland for customer supply
cable
Note
Further signal lines might be needed, please check your specific
wiring diagram.
Содержание CEMcaptain GAA610-M
Страница 56: ...56 GAA610 M ADVANCED EMISSION GAS MONITORING SYSTEM OI GAA610 M EN REV B 11 Operation Menu structure ...
Страница 97: ...GAA610 M ADVANCED EMISSION GAS MONITORING SYSTEM OI GAA610 M EN REV B 97 Location diagram ...
Страница 98: ...98 GAA610 M ADVANCED EMISSION GAS MONITORING SYSTEM OI GAA610 M EN REV B 18Appendix Piping diagram ...