Open spanner. Refer to

section 

10.5

.

Procedure

1. Carefully lower the cabinet on the

foundation. Refer to section 

4.3

. Make

sure that the holes in the cabinet (A)

and the foundation (B) are aligned.

Caution: Make sure that

there is no kink in the

cables.

2. Install the fasteners (C).

3. Tighten the fasteners.

5.6

Electrical installation

5.6.1

Electrical installation procedure

Preliminary requirements

Installation engineer

Procedure

1. Open the front and right doors. Refer to section 

8.1

.

2. Connect the PE wire. Refer to section 

5.6.2

.

3. Connect the enclosure to the earth. Refer to section 

5.6.3

.

4. Connect the wires of the AC input cable. Refer to section 

5.6.4

.

5. If it is necessary, connect the Ethernet cable. Refer to section 

5.6.5

.

6. Close the doors. Refer to section 

8.2

.

5.6.2

Connect the PE wire

Preliminary requirements

The front and right doors

are open.

Cable lugs and fasteners.

Refer to section 

10.6

.

Installation engineer

C

A

B

Installation

9AKK108466A3703-EN | 001

49

Содержание ADC-90-200-C1

Страница 1: ...tegration into In Control In Charge s EVSE management platform LTE Modem and LAN TUV Certified Specifications Max Output Voltage 90kW Max share the same housing Available with CCS1 Dual CCS1 and Dual...

Страница 2: ...Interface Value Charging Connectors CCS1 CHAdeMO HMI 7 TFT LCD Display Communication OCPP 1 6J Network Connection GSM 3G 4G modem 10 100 Base T Ethernet RFID ISO IEC 14443A B Mifare Calypso Language...

Страница 3: ...Operation and installation manual Terra 94 104 124 184 North America Copyright 2022 ABB All rights reserved...

Страница 4: ...Copyright All rights to copyrights registered trademarks and trademarks reside with their respective owners Copyright ABB EV Infrastructure All rights reserved 2 9AKK108466A3703 EN 001...

Страница 5: ...Liability 14 2 2 General safety instructions 14 2 3 Responsibilities for the owner 14 2 4 Required qualifications for the installation engineer 15 2 5 Personal protective equipment 15 2 6 Safety instr...

Страница 6: ...n Fair Share 34 3 9 External residual current device 34 3 10 Description of the touchscreen 35 3 10 1 General description of the layout 35 3 10 2 General description of the buttons 36 3 11 Local Servi...

Страница 7: ...52 5 7 1 General procedure 52 5 7 2 Install the bracket of the tilt sensors 52 5 7 3 Install the tilt sensors 53 5 7 4 Connect the tilt sensors 53 5 7 5 Install a ferrule on a wire 54 5 7 6 Connect a...

Страница 8: ...72 9 1 Troubleshooting procedure 72 9 2 Troubleshooting table 72 10 Technical data 73 10 1 EVSE type 73 10 2 General specifications 73 10 3 Parts included in the delivery 74 10 4 Transport specificat...

Страница 9: ...4 EVSE derating in heavy duty operation 88 10 15 Harmonics on the grid 89 10 15 1 Terra 184 89 10 15 2 Terra 124 and 104 91 10 15 3 Terra 94 92 10 16 AC input specifications 94 10 16 1 General AC inp...

Страница 10: ...For the required qualifications for the instalaltion engineer refer to section 2 4 1 3 Revision history Version Date Description 001 January 2022 Initial version 1 4 Language The original instruction...

Страница 11: ...o not obey the instruction this can cause injury or death Refer to section 1 10 Warning If you do not obey the instruction this can cause injury Refer to section 1 10 Caution If you do not obey the in...

Страница 12: ...or signal words are present in this document 1 10 Special symbols for warnings and dangers Symbol Risk type General risk Hazardous voltage that gives risk of electrocution Risk of pinching or crushing...

Страница 13: ...s Boulevard Saint Laurent AZ 85284 Qc H4S 0B5 Canada Phone 800 435 7365 E mail CA evci us abb com Contact data ABB EV Infrastructure in your country can give you support on the EVSE You can find the c...

Страница 14: ...s CHAdeMO Abbreviation of CHArge de MOve a standard charging method for electric vehicles Contractor Third party that the owner or site operator hires to do engineering civil and electrical installati...

Страница 15: ...Front side face forward to the EVSE during normal use B Left side C Right side D Rear side X X direction positive is to the right Y Y direction positive is rearward Z Z direction positive is upward Ab...

Страница 16: ...l rules obey the stricter between the requirements and procedures specified in this document and the local rules 2 3 Responsibilities for the owner The owner is the person who runs the EVSE for commer...

Страница 17: ...installation engineers obey the local rules the installation instructions and the specifications of the EVSE 2 5 Personal protective equipment Symbol Description Protective clothing Safety gloves Safe...

Страница 18: ...ke into account the mass and the center of gravity of the EVSE Obey the safety instructions that apply to the hoisting equipment or the forklift truck Put on the correct personal protective equipment...

Страница 19: ...not all symbols are present on the EVSE 2 11 Discard the EVSE or parts of the EVSE Incorrect waste handling can have a negative effect on the environment and human health due to potential hazardous s...

Страница 20: ...continuously ensure a secure connection between the product and Owner s network or any other network as the case may be The Owner shall establish and maintain any appropriate measures such as but not...

Страница 21: ...manufacturer E Serial number F EVSE mass G EVSE rating H Address of the manufacturer I Symbol of local certification J QR code with the internal product code for the manufacturer K QR code with the se...

Страница 22: ...anger General risk If you use the EVSE in any other way than described in the related documents you can cause death injury and damage Use the EVSE only as intended Description 20 9AKK108466A3703 EN 00...

Страница 23: ...3 3 Working principles 3 3 1 Terra x4 variants CC and CJ A B D D G G E J K M L N O P Q R S T W X Y U V V I H C F F F F F F J K M L I H Description 9AKK108466A3703 EN 001 21...

Страница 24: ...oard N Interlink contactor O AC SPD P RCD breaker Q Auxiliary transformer R Auxiliary breaker S Heater T Power supply unit U DC EMC filter V DC cooling fans W CCB board X HMI Y Power bridge board Blac...

Страница 25: ...3 3 2 Terra x4 variant C A B D D G G E J K M L N O P Q R S V W X T U U I H C F F F F F F Description 9AKK108466A3703 EN 001 23...

Страница 26: ...fans V CCB board W HMI X Power bridge board Black and bold lines power connection Black and thin lines auxiliary power connection Green lines CAN bus Purple lines control signal or monitoring signal...

Страница 27: ...n the air outlet E Border cover F EV charge connector holder G Connector H Plate over the RFID reader and the integrated payment terminal I Emergency stop button J Touchscreen K Right door L Enclosure...

Страница 28: ...e EVSE Antenna To send and receive wireless 3G and 4G signals 3 4 3 Overview of the EVSE inside F J H I G A B C D E K A Main breaker 2 B Main breaker 1 C PE busbar D Auxiliary breaker E Fused surge pr...

Страница 29: ...nect the AC power input to or from the auxiliary power for the control circuit Auxiliary breaker To connect or disconnect the AC power input from the auxiliary AC fuse to the auxiliary transformer Pow...

Страница 30: ...stalled EVSE A B C D A EVSE B Base C Floor D Foundation 3 4 6 Overview of the cable management system option C B A I D E F G H A Duct B Wheel C Top attachment point D Gland E Cable clamp Description 2...

Страница 31: ...from the manufacturer or from an external company that offers authorization solutions via OCPP 3 6 Payment terminal The touchscreen guides the user how to use the payment terminal Note To use and adju...

Страница 32: ...3 7 4 Integrated payment terminal The manufacturer can deliver the EVSE with different payment terminals The available options vary depending on the region and country where the EVSE is installed If y...

Страница 33: ...uit breaker 24 V DC supply delivered from an UPS and all other components are not within the scope of ABB E Mobility therefore are not provided in the EVSE The owner is responsible for considering a v...

Страница 34: ...ed for sequential power allocation it can serve one EV at a time with DC fast charging In this configuration the EV charging power is the maximum power available to the EVSE the rated power output Eff...

Страница 35: ...econd EV will also receive up to half of the maximum power available to the EVSE When one of the charge sessions ends this will not change the maximum amount of power that is delivered to the other ch...

Страница 36: ...wer can reach up to the maximum power available to the EVSE up to the rated power output of the station Effectively the maximum power output can be less than the rated power output because of power co...

Страница 37: ...city of the AC input power part of the EVSE The amplitude of the current peaks can change These factors are the source of the differences The location of the EVSE The power grid The earth impedance Fo...

Страница 38: ...selected language start Start To start the charge session stop Stop To stop the charge session 3 11 Local Service Portal The Local Service Portal is a service tool available on the EVSE for these purp...

Страница 39: ...on to go to the Hardware test screen Action button Trigger discovery to install new software Hardware test screen To navigate to various hardware tests Configuration main screen To set the following d...

Страница 40: ...to section 4 2 2 2 Remove the packaging material 3 Discard the packaging material Refer to section 2 11 4 Do a visual check for damage on the outside and inside of the EVSE 5 Make sure that all parts...

Страница 41: ...on d If you see damage on the cabinet through the packaging material do not unpack the EVSE e Contact the manufacturer and give details of the delivery problems Refer to section 1 12 4 2 3 Remove the...

Страница 42: ...r bolts with lifting loops A 2 Connect the cables B of the hoisting equipment to the swivel eye bolts or bolts with lifting loops 3 Move the cabinet to the correct location 4 3 2 Move the cabinet with...

Страница 43: ...Procedure 1 Move the forks A of the forklift truck in the gaps at the side of the cabinet 2 Move the cabinet to the correct location A Inspection and transport 9AKK108466A3703 EN 001 41...

Страница 44: ...efer to section 4 2 1 c Move the cabinet to the correct location Refer to section 4 3 2 If a lower installation of the EVSE is required for wheelchair accessibility remove the base Refer to section 10...

Страница 45: ...rdance with the safety instructions Refer to section 2 8 Ethernet cable if no wireless 2G 3G 4G signal is available Refer to section 10 13 Contact the manufacturer if you require a specific configurat...

Страница 46: ...3 2 Prepare a casted foundation Preliminary requirements The cover of the removed Concrete drill Wire cutter Installation engineer Concrete Procedure 1 Dig the hole A for the casted foundation For th...

Страница 47: ...ion is ready Refer to section 5 3 Hoisting equipment The manufacturer delivers the EVSE with a standard base For specific requirements the owner can decide to replace this standard base with an altern...

Страница 48: ...evant if it is not possible to pull the AC power cables through the concrete foundation In that situation you can lay the power cables on the floor guide them through a conduit and let them enter from...

Страница 49: ...authorized locations because this can compromise the structural integrity of the base with side entrance 3 Guide the cables to the cable trays 4 Align the frame B with the threaded holes 5 Install the...

Страница 50: ...requirements The front and right doors are open The cable inlet is open Installation engineer Procedure 1 If it is necessary install the cable gland A over the Ethernet cable B 2 Guide the wire C of...

Страница 51: ...quirements Installation engineer Procedure 1 Open the front and right doors Refer to section 8 1 2 Connect the PE wire Refer to section 5 6 2 3 Connect the enclosure to the earth Refer to section 5 6...

Страница 52: ...se the fasteners D 3 Tighten the fasteners to the correct torque For the specification refer to section 10 7 5 6 3 Connect the enclosure to the earth Preliminary requirements Installation engineer Mak...

Страница 53: ...insulation from the end of the wires Make sure that the strip length is compatible with the cable lugs E c Attach the cable lugs to the end of the wires Use the cable lug tool 2 Attach the wires to t...

Страница 54: ...ications of the tilt sensors refer to section 10 10 1 Install the bracket A Refer to section 5 7 2 2 Install the tilt sensors B Refer to section 5 7 3 3 Connect the tilt sensors Refer to section 5 7 4...

Страница 55: ...es Procedure 1 Connect these parts in the bottom DIN rail Terminal block A x2 Terminal plate for the terminal block B 2 Carefully guide the tilt sensor cable Make sure that the tilt sensor cable does...

Страница 56: ...er to 10 7 5 7 5 Install a ferrule on a wire Preliminary requirements Wire cutter Wire stripper pliers Crimp plier Ferrule Procedure 1 Make sure that the diameter of the ferrule is correct The ferrule...

Страница 57: ...top of the EVSE EV charge cables 2 Put the cable management system horizontally 3 Remove the travel bolt A 4 Do a check on the number of counterweights that are required for the EV charge cable Refer...

Страница 58: ...ease the wire The EV charge cable folds with one loop depending on the cable length 5 8 3 Install the cable management system 1 Install the head A on the EVSE in the eyebolt hole 2 Tighten the fastene...

Страница 59: ...e The site operator or owner is available to receive instructions from the service engineer of the manufacturer 3 Make sure that this data is available Contact data of the contact person on site Addre...

Страница 60: ...ician from the manufacturer or a third party to use the EVSE after commissioning After approval do not move the EVSE 5 Make sure that the space around the EVSE cannot get blocked Think of snow or othe...

Страница 61: ...harge session Refer to section 6 4 2 4 Stop the charge session Refer to section 6 4 3 6 4 2 Start a charge session Preliminary requirements Owner Procedure 1 On the touchscreen select the applicable c...

Страница 62: ...locks the connector to the EV To unlock the connector obey the instructions for the EV 4 Put the EV charge cable in the holder on the EVSE 6 5 Energize the EVSE Preliminary requirements Owner Procedu...

Страница 63: ...lose the doors Refer to section 8 2 6 6 2 Measure the AC voltage Preliminary requirements Owner Only do this procedure if a different procedure refers to this procedure Voltage tester Refer to section...

Страница 64: ...Refer to section 8 1 2 Set the main breakers 1 and 2 to the off position a Set the main breakers from the Auto to the Manual position b Set the main breakers from the Manual to the Off position 3 Ene...

Страница 65: ...onds 3 Set Authorization to ON or OFF Use the toggle button 4 Set the maximum AC input current in amperes The AC input current field has no maximum value The correct AC input value is the responsibili...

Страница 66: ...ss is finalized The discovery of new hardware can take up to 15 minutes At the end of the discovery process the new software is installed The system starts the processes again in the background and th...

Страница 67: ...uired spare parts refer to section 10 22 Replace the filters for the air outlets After the first year then 2 years Refer to section 7 5 7 2 Clean the cabinet Preliminary requirements Owner Cleaning ag...

Страница 68: ...ions and instructions 7 3 Do a visual check of the EVSE Preliminary requirements Owner Procedure 1 Do a visual check for damage on these parts Part Damage EV charge cables and connectors Cracks or rup...

Страница 69: ...on that is indicated on the air inlet filter corresponds with the air flow 6 Install these parts 1 Clean air inlet filter 2 Cover 7 Tighten the nuts 8 Do the steps 3 to 7 again for the other air inlet...

Страница 70: ...come off 6 Install the new air outlet filter Make sure that the air flow direction that is indicated on the air outlet filter corresponds with the air flow 7 Push the cover to the rear 8 Tighten the...

Страница 71: ...r key for each cabinet Procedure 1 Unlock the lock A of the front door B Use the door key 2 Open the front door 3 If necessary open the left or right doors C through the opening of the front door 8 2...

Страница 72: ...he front door B 3 Lock the lock C of the front door Use the door key 8 3 Remove the border covers Preliminary requirements Installation engineer Set of hex keys Note This procedure is only valid for a...

Страница 73: ...uirements Installation engineer Set of hex keys Note This procedure is only valid for a standard base or a base with side entrance Procedure 1 Install these parts 1 Border covers A 2 Fasteners B B B A...

Страница 74: ...touchscreen shows this message Unable to lock the connector The EV charge cable is not connected correctly to the EV Connect the EV charge ca ble to the EV correctly You are not authorized for the ch...

Страница 75: ...ant UL UL compliant EV charger cable connec tion C C1 CCS 1 connector C C2 CCS 2 connector J CHAdeMO EV charge cable length 4 4 m 13 ft 6 6 m 20 ft Connector type A Air cooled EV charge cable s Power...

Страница 76: ...eter Specification CCS 1 and CCS 2 CHAdeMO Voltage rating of the connectors on the EVSE 200 1000 V DC 150 500 V DC Maximum voltage that the EVSE can de liver 920 V DC 500 V DC In Japan 450 V DC Power...

Страница 77: ...th socket and extension Size M5 8 mm and M6 10 mm Size M5 0 31 in and M6 0 39 in Voltage tester Standard To make sure that the RCD works press the test but ton on the RCD Digital multimeter Standard H...

Страница 78: ...ture 40 C to 70 C 40 F to 158 F Operation temperature range 35 C to 50 C 31 F to 122 F Maximum altitude above sea level 2000 m 6500 ft Note Operation of the EVSE outside the operating temperature rang...

Страница 79: ...r use and UV protected Minimum test 1 5 kV Strip length 11 mm 0 43 in Voltage rating 600 V Shielded wire Not required 10 10 3 Wiring diagram for the tilt sensors V GND NC COM 24 Vdc 0 Vdc NC COM E A C...

Страница 80: ...Width of the base X2 Distance between the outer fixation holes X3 Distance between 2 fixation holes Y1 Depth of the base Y2 Distance between the 4 fixation holes Y3 Distance between the outer fixation...

Страница 81: ...2 64A See CCS 1 400A 4 13 BP 1394 2 82A 50 50 4 CCS 1 400A 6 20 BP 1394 2 82A 30 70 5 CCS 1 400A 8 26 BP 1394 2 82A See CHAdeMO 200 A 4 13 BP 1394 3 55A 50 50 5 CHAdeMO 200 A 6 20 BP 1394 3 55A 30 70...

Страница 82: ...n 8 m 26 ft the EVSE is not compliant with NEC 625 17 An external cable management system must be installed to comply with the standard 10 12 2 Packaged product The EVSE is mounted on a standard size...

Страница 83: ...nterweight 3 6 6 The number of counterweights depends on the cable installed on the EVSE For the suggested number of counterweights refer to section 10 11 10 12 4 Center of gravity X Z Y A A Center of...

Страница 84: ...ere the bollards can be installed C Wall or other obstacles X1 Free space required on the sides of the EVSE X2 Width of the EVSE X3 Free space required on the sides of the EVSE Y1 Free space required...

Страница 85: ...he fasteners of the EVSE B Conduit stub up C Addtional holes D Front of the EVSE Parameter Specification mm in A M10 depth 60 M10 depth 2 4 B 25 50 1 2 C 50 75 2 3 X1 565 22 2 X2 36 5 1 4 X3 189 7 4 X...

Страница 86: ...the hole Y2 Depth of the hole Z2 Height of the hole Z3 Distance of the foundation above the ground level Parameter Specification mm in X1 626 24 6 Y1 700 27 6 Z1 600 23 6 X2 680 26 8 Y2 754 29 7 Z2 58...

Страница 87: ...base Y2 Depth of the base including the fasteners Y3 Distance between the outer fixation holes Y4 Distance between the middle fixation holes Z Height of the base Parameter Specification mm in X1 450...

Страница 88: ...ble elements Z3 Z4 Z5 Z2 Z1 Z6 A A Ground level Z1 Maximum height of the user operable elements according to ADA Z2 Lowest height of the user operable elements according to ADA Z3 EVSE highest user op...

Страница 89: ...s Note It is the responsibility of the installer to make sure that the EVSE complies with ADA requirements 10 13 Communication interface specifications General specifications Parameter Specification R...

Страница 90: ...90 10 41 45 105 113 85 15 46 50 114 122 75 25 51 55 123 131 65 35 The output power of the EVSE can be limited by the temperature of the charge connector This limitation can be caused by the connector...

Страница 91: ...0 2984 Order Phase L1 Phase L2 Phase L3 IRMS HDF IRMS HDF IRMS HDF A A A 1 225 10 100 00 225 25 100 00 225 04 100 00 2 0 17 0 07 0 66 0 30 0 64 0 29 3 0 57 0 25 0 52 0 23 1 08 0 48 4 0 42 0 19 0 17 0...

Страница 92: ...0 04 0 16 0 07 0 23 0 10 33 0 04 0 02 0 07 0 03 0 09 0 04 34 0 12 0 06 0 18 0 08 0 14 0 06 35 0 50 0 22 0 50 0 22 0 57 0 25 36 0 14 0 06 0 08 0 03 0 18 0 08 37 0 46 0 21 0 41 0 18 0 51 0 23 38 0 15 0...

Страница 93: ...12 0 16 0 11 12 0 11 0 07 0 13 0 08 0 23 0 16 13 0 51 0 34 0 54 0 36 0 50 0 33 14 0 17 0 11 0 10 0 06 0 09 0 06 15 0 06 0 04 0 08 0 06 0 13 0 09 16 0 17 0 11 0 17 0 12 0 16 0 11 17 0 55 0 37 0 51 0 3...

Страница 94: ...03 0 01 0 01 47 0 18 0 12 0 16 0 11 0 14 0 09 48 0 10 0 06 0 06 0 04 0 13 0 09 49 0 18 0 12 0 14 0 09 0 11 0 08 50 0 06 0 04 0 02 0 02 0 04 0 02 Total 151 24 2837 150 86 2889 151 02 2838 10 15 3 Terra...

Страница 95: ...30 0 31 0 27 26 0 10 0 09 0 06 0 06 0 09 0 08 27 0 02 0 02 0 04 0 04 0 06 0 06 28 0 10 0 09 0 07 0 07 0 14 0 13 29 0 26 0 23 0 25 0 22 0 30 0 26 30 0 04 0 04 0 09 0 08 0 13 0 12 31 0 29 0 26 0 29 0 2...

Страница 96: ...16 1 General AC input specifications Parameter Specification Input AC power connection 3P PE WYE input Input voltage range 480 VAC 10 60 Hz Power factor at full load 0 96 Efficiency 94 at nominal outp...

Страница 97: ...and local regulations Material Copper and aluminium Maximum temperature of the input wires 75 C 167 F Diameter of each AC wire including shielding 34 to 45 mm 1 3 1 8 in 10 16 3 Terra 94 Parameter Spe...

Страница 98: ...um rated input current 230 A Recommended input circuit breaker 300 A Maximum power dissipation 191 3 kVA Short circuit current rating 65 kA Maximum size of the input wire 500 kcmil Note Power limiting...

Страница 99: ...300 A high current model CHAdeMO 200 A Output current in function of output voltage 0 100 200 300 400 500 600 100 200 300 400 500 600 700 800 900 1000 Output current A output voltage V CCS 200A CHAdeM...

Страница 100: ...kW Current A Power kW 0 0 0 0 0 0 200 30 200 40 300 60 200 40 200 60 300 90 200 60 200 80 225 90 200 80 150 90 150 90 180 90 113 90 113 90 10 17 3 Terra 104 Parameter Specification DC output power on...

Страница 101: ...500 100 200 300 400 500 600 700 800 900 1000 Output current A output voltage V CCS 200A CHAdeMO 200A CCS High Current 400A Charger Capacity Voltage V Current A Power kW 150 0 0 150 320 48 200 400 80...

Страница 102: ...200 300 400 500 600 700 800 900 1000 0 20 40 60 80 100 120 140 160 180 200 CHAdeMO CCS 200 A 200 A High Current 400 A Current A Power kW Current A Power kW Current A Power kW 0 0 0 0 0 0 200 30 200 4...

Страница 103: ...t 400A Output current kW output voltage V 100 200 300 400 500 600 700 800 900 1000 0 50 100 150 200 250 300 350 400 450 500 Charger Capacity Voltage V Current A Power kW 150 0 0 150 320 48 200 400 80...

Страница 104: ...rrent A Power kW Current A Power kW 0 0 0 0 0 0 200 30 200 40 200 40 200 40 167 50 167 50 167 50 125 50 125 50 125 50 83 50 83 50 100 50 63 50 63 50 10 17 4 Terra 124 Parameter Specification DC output...

Страница 105: ...t 400A Output current A output voltage V 100 200 300 400 500 600 700 800 900 1000 0 50 100 150 200 250 300 350 400 450 500 Charger Capacity Voltage V Current A Power kW 150 0 0 150 320 48 200 400 80 3...

Страница 106: ...600 700 800 900 1000 0 50 100 150 200 250 300 350 400 450 500 Output power A CHAdeMO CCS 200 A 200 A High Current 400 A Current A Power kW Current A Power kW Current A Power kW 0 0 0 0 0 0 200 30 200...

Страница 107: ...A output voltage V 100 200 300 400 500 600 700 800 900 1000 0 50 100 150 200 250 300 350 400 450 500 Output current A Output current A Charger Capacity Voltage V Current A P kW 50 0 0 150 320 48 200 4...

Страница 108: ...nt A Power kW Current A Power kW 0 0 0 0 0 0 200 30 200 40 200 40 200 40 200 60 200 60 200 60 150 60 150 60 150 60 100 60 100 60 120 60 75 60 75 60 10 17 5 Terra 184 Parameter Specification DC output...

Страница 109: ...t 400A output voltage V 100 200 300 400 500 600 700 800 900 1000 0 50 150 150 200 250 300 350 400 450 500 Output current A Charger Capacity Voltage V Current A Power kW 150 0 0 150 480 72 200 600 120...

Страница 110: ...00 600 700 800 900 1000 0 20 40 60 80 100 120 140 160 180 200 Output power A CHAdeMO CCS 200A 200A High Current 400A Current A Power kW Current A Power kW Current A Power kW 0 0 0 0 0 0 200 30 200 40...

Страница 111: ...t 400A output voltage V 100 200 300 400 500 600 700 800 900 1000 0 50 150 150 200 250 300 350 400 450 500 Output current A Charger Capacity Voltage V Current A Power kW 150 0 0 150 480 72 200 600 120...

Страница 112: ...nt A Power kW Current A Power kW Current A Power kW CHAdeMO 200A CCS 200A CCS High Current Peak 400A Current A Power kW Current A Power kW Current A Power kW 0 0 0 0 0 0 200 30 200 40 300 60 200 40 20...

Страница 113: ...50 Terra 184 170 Rated peak withstand current kA peak Parameter Specification kA Terra 94 6 625 Terra 104 6 625 Terra 124 6 625 Terra 184 6 625 Rated short time withstand current kA rms Parameter Spec...

Страница 114: ...er procedure R Replacement 10 21 Cleaning specifications Parameter Specification Cleaning agent pH value between 6 and 8 Non abrasive tool Non woven nylon hand pad 10 22 Spare parts Part Name Quantity...

Страница 115: ...le 1 x Terra x4 CJ 2 x Terra x4 JJ Gun holder 1 x for CCS type 1 UL connection 1 x for CCS type 2 CE connection 1 x for ChadeMo connection Rain cap for the gun holder 1 x for CCS type 1 UL connection...

Страница 116: ...11 Appendix 11 1 Declaration of conformity Appendix 114 9AKK108466A3703 EN 001...

Страница 117: ...Appendix 9AKK108466A3703 EN 001 115...

Отзывы: