Checklist before mechanical installation
The installation site
Check the installation site. See the technical data for the allowed operating conditions and for the re-
quirements for free space around the converter.
Check that the floor that the converter is installed on is of non-flammable material, as smooth as possible,
and strong enough to support the weight of the converter.
Check the floor flatness with a spirit level. The maximum allowed deviation from the surface level is
5 mm (0.2 in) in every 3 meters (9.8 ft).
If necessary, level the installation site, as the cabinet is not equipped with adjustable feet.
Check that the wall behind the converter is of non-flammable material.
Required tools
Check that you have following tools for moving the converter to its final position, fastening it to the floor
and tightening the connections:
• crane or fork-lift (check the load capacity); iron bar and piece of planked wood
• Pozidriv and Torx (2.5 … 6 mm, 0.98 … 0.2 in) screwdrivers for the tightening of the frame screws
(Screws needed for fastening the cabling boxes and other accessories delivered by ABB are included
in the delivery. They are inside the cabinet. The delivery does not contain screws or tools to install
the cabinet to the floor.)
• torque wrench
• set of wrenches and sockets.
The delivery
For unpacking the delivery, see page
Check that the delivery contains:
• converter cabinet (parallel converters: both converter cabinets of the same delivery)
• cabling boxes for the generator-side converter
• option modules (installed at the factory)
• DC chopper(s) and DC resistor(s) (optional)
• filters of the door air inlets
• appropriate wind turbine converter manual(s) and option module manual(s)
• delivery documents (dimension drawings, circuit diagrams, etc.)
The manual(s) are delivered inside the converter.
Check that there are no signs of damage.
Check the information on the type designation label of the converter to verify that the delivery is of correct
type.
42 Mechanical installation
4
Содержание ACS880-77CC
Страница 1: ...ABB WIND TURBINE CONVERTERS ACS880 77CC wind turbine converters Hardware manual...
Страница 2: ......
Страница 4: ......
Страница 10: ...10...
Страница 17: ...5 1 3 4 6 8 7 2 Safety instructions 17...
Страница 22: ...22...
Страница 40: ...40...
Страница 60: ...60...
Страница 73: ...2a 3b 4c 5 Air flow direction is towards the converter module Maintenance 73...
Страница 104: ...104...
Страница 108: ...Description CAN bus connection XCAN XCAN 108 BCU x5 control unit...
Страница 112: ...112 Dimension drawings...
Страница 113: ...Dimension drawings 113...
Страница 114: ...114 Dimension drawings...
Страница 126: ...126...