O
VERHEAD
14) Assemble two Overhead beams using (6 sets)
M10 x 20 bolt, nut, flat washer, and lock washer
as shown in
Fig 6
. Hand-tighten bolts to allow
adjustment if needed.
Fig 6 – Overhead
15)
Use 2 sets M10X20 bolt, nut, flat washer,Install
Overhead Limit Switch bracket to the Overhead
Beam on the Power Side of the hoist.
See Fig 7a:
Fig 7a – Overhead Limit Switch Power Side
16)
Use 2 sets M10X20 bolt, nut, flat washer,Install
bracket to the head Beam on the Idler side of the
hoist.
See Fig 7b:
Fig. 7b – Overhead Limit Switch Idler Side
S
YMMETRIC
17
) With the Overhead positioned
UPSIDE DOWN
,
assemble the cable sheaves, spacers, and pins
as shown in
Fig 8
below.
Fig 8 – Symmetric Sheave Assembly
19
Содержание AutoLift AL-9500HD
Страница 10: ...1140 635 950 1350 3550 9 2505 3615 ...
Страница 11: ...5 0 Introduction 5 1 Control Board WALL 1m WALL 3m Vehicle Enter 1m WALL Fig 1 10 ...
Страница 24: ...23 ...
Страница 29: ...10 0 Hydraulic System Diagram 28 ...
Страница 30: ...11 0 Balance Rope Diagram 29 ...
Страница 33: ...13 0 Parts List 32 ...
Страница 34: ...33 ...
Страница 35: ...34 ...
Страница 36: ...35 ...