Operating and Assembly Instructions – A.B.S. Flexilo ECO for wood pellets
Final inspection
Subject to technical change
Issue 09/2016
Page 26 of 32
©A.B.S. Silo- und Förderanlagen GmbH
6
Final inspection
Position of the extraction device
Check that the discharge neck is centered in the silo. Adjust the silo or extraction unit so that
the silo is centered exactly over the point of discharge.
•
Check that all individual parts are bolted together properly.
•
Check that the top bars and frame legs (stands) are not askew (use a spirit level).
•
Check that the silo bag is suspended centrally.
•
Check that the filling and extraction systems are attached correctly.
•
Check the floor clearance.
•
Check that the nameplate is attached in a clearly visible location on a frame leg or the
filling line.
•
Check the room layout (wall and ceiling clearance, condition of the room, fixtures in the
room, room ventilation).
•
Have the frame earthed by a licensed electrician. The earth resistance must not exceed
106
Ω
.
•
Check that the silo frame is anchored to the floor properly.
•
Check that the silo cover is suspended correctly.
•
Check the stability of the silo frame overall.
•
Close any unused filling openings attached to the support frame.
•
Check that the filling pipe is attached securely.
•
Tighten the clamp rings and hose clamps once again.
•
Tighten the clamping rings and tension bands on the extraction system once again.
•
Conduct a test run of the extraction system using a few sacks of material prior to filling for
the first time.
Use the following check list to ensure proper assembly of the silo.
FALSCH
RICHTIG
FALSCH
RICHTIG
Right
Wrong