background image

6

© Copyright 2017 Zoeller

®

 Co. All rights reserved.

Outdoor Prepackaged System Installation Instructions

This set of instructions is for factory prepackaged outdoor progressing cavity grinder systems only.  If this is a field assembled outdoor system you can 

use these instructions as a guideline.

Operation

GENERAL

Zoeller pumps are lubricated and tested at the factory prior to shipment and require 

minimum pre-start-up maintenance.
Maximum operating temperature of pump liquid for grinder pumps must not exceed 130°F 

(54°C).
These units are not designed to handle liquids other than sanitary sewage. If pump is 

used to dewater areas with contaminated liquids with heavy or abrasive materials, the 

warranty will be voided.

NAMEPLATE DATA

The nameplate, located on the top of the pump, indicates specific information about 

the construction of the pump. The model number and date code information should be 

recorded on the front page in the “Owner’s Information” section of this manual.

SHORT TERM STORAGE

When not in use, the pump should be stored and the following is advised:

•  Drain pump housing by laying pump horizontal with discharge down. Then stand pump 

on legs.

•  Store pump inside whenever possible or cover with some type of protective covering.

•  Tape or seal in plastic bag the terminal ends of wire leads.

•  Spray coat unpainted surfaces with rust inhibiting oil.

•  The impeller should be rotated every six months in order to keep the seal lubricated 

and not develop a permanent set.

If panel is to be stored, the following is advised:

•  Store the panel inside whenever possible and leave in the shipping box.

•  All openings shall be sealed.

•  Store in an upright position.

•  Do not stack anything on top of panel.

START-UP PROCEDURE

Before placing the equipment into operation the following should be checked:

•  Clean pit.

•  Electrical boxes dry and securely installed.

•  Floats positioned properly.

•  Discharge valves open.

•  Adequate water level in basin for pump submersion.

Once the above has been verified proceed with the following checks:

•  Pump power cables and control floats properly installed and voltage verified.

•  Conduit connections to panel are properly sealed.

•  After installing the pump into the basin, with adequate submergence, open the 

discharge valve fully. Start the unit using manual controls. If flow is appreciably less 

than rated performance, pump may be air locked. To expel trapped air, jog the unit 

several times, using the manual controls.

•  Have a qualified electrician take voltage and current measurements  with the pump 

running. Record these readings in the space provided in the 

“Owner’s Information” 

section on page 1 of this manual for future reference. 

ADJUSTMENT PROCEDURE

Pumps:  No adjustments are required.

Floats:   Refer to the system drawing or to the panel wiring schematic for the desired 

location of each float switch setting. The off switch should deactivate the 

pump before the water level drops to the mid-point of the pump.

Valves: 

Discharge valves should be placed in the fully open position. Systems should 

not be operated for extended periods of time with the discharge valves partially 

closed due to damaging the valve. Check for an anti-siphon valve when used 

in a pressure sewer.

SHUTDOWN PROCEDURES

If a system is shutdown for more than six months, the following is recommended:

Pumps:  If pit is to remain dry, then the pump can remain in the pit. Do not run dry. If 

the pit is to remain wet, the pump should be removed and stored as noted 

above.

Panels:  The panel should have all openings sealed to prevent moisture and dust from 

entering the enclosure. Prior to restarting system, the panel should be inspected 

for presence of moisture and any loose connections.

Valves: 

Consult the valve/actuator supplier for information concerning these systems 

components.

  1.  Review the drawing in Fig. 4 on page 5 and the actual system to become familiar 

with the components in the packaged grinder pump system.  Review where the unit 

will be installed.  Determine where the power feed, inlet pipe, and discharge pipe will 

be located.

  2.  Remove the unit from packing.  Prepackaged outdoor systems are preassembled at 

the Zoeller Company and require a minimum of field assembly work.  Float switches 

are set and tethered for proper operation from the Factory.  The alarm switch should 

be located 2” above the pump “on” level.

  3.  Float switches are tied in place for shipping purposes on all model prepackaged 

systems.  Cut the cable tie around each float switch bulb or the unit will not operate 

properly.  Verify that where the float switches are set will work for your application.  

Verifying that the float switches are set properly and will not hang up inside 

the basin is the responsibility of the installing contractor. 

  4.  Dig a hole for the basin.  The hole should be at least 24” larger in diameter than 

the basin diameter to provide 12” of backfill all around and deep enough to provide 

either 12” of compacted backfill or 6” when a concrete pad is required.  Ensure the 

removable cover extends above the finished grade line and the grade slopes away 

from the unit.  Backfill and subbase should be 1/8” –3/4” pea gravel or 1/8” –1/2” 

crushed stone.  (Reference basin installation instructions included with unit)

 5. 

Note:  Care must be taken when excavating in order to avoid underground 

utilities and disturbance of existing structure foundations.  The hole should 

be located at least ten feet from adjacent structures.  Additional distance may 

be required to sufficiently locate the basin outside of the loading area of the 

adjacent structures.

  6.  The location of the inlet fitting is determined by the depth of the inlet pipe.  The inlet fitting 

must be used with 4” pipe.  It is best to install the inlet on the side of the basin opposite 

the float switches.  To install, use a 5” hole saw to drill into the side of the basin at the 

correct elevation.    Center the hub inner diameter with the hole in the basin.  Attach 

the hub to the side of the basin using the sealant and hardware provided.

  7.  The bottom of the excavation can now be back filled and compacted.  Set basin in 

hole and connect the 4” inlet pipe to the inlet hub.  

  8.  The discharge piping is connected to the 1-1/4” threaded fitting located in the 

basin sidewall.

  9.  Connect pull rod to Pump assembly.  Connect lift cable to top of pump.  Lower the 

pump into basin ensuring the discharge pipe bracket slides into the disconnect fitting.

  10.  Pouring a concrete anchor around system can now be completed.   Basin should be 

filled with water when pouring concrete to minimize movement of the system.  Back 

fill around basin with specified media.  Care should be used to avoid damaging 

components or leaving voids when back filling.  Refer to Basin installation reference 

guide on more specific requirements.

 11. 

Note: The progressing cavity grinder basin is a sewage holding tank.  Vent 

connection should be installed in accordance with all national, state and local 

plumbing codes.  

  12.  Dig a trench for the electrical conduit.  Trench should be located at least 18” deep 

and follow all applicable NEC codes.  Connect electrical wiring to Junction box 

according to wiring instructions included in this manual and wiring diagram in box.  

Use the potting kit provided with the junction box. Use the included sealant when 

closing junction box.

  13.  If used, a control panel is installed within sight of the system.  Connect float switches 

and pump cords according to the “Pump Wiring Instructions” found in this manual 

and located inside the panel enclosure.

  14.  Remove any debris from the basin.  Using clean water, check the system for 

proper operation.

  15.  Seal and secure the lid using the proper bolts and sealant when using a lid without 

a formed gasket. 

  16.  Add water to the basin and test the system for leaks and proper pump operation.

  17.  Record system start up data for future reference.

Summary of Contents for 810 Series

Page 1: ...mited Warranty Checklist and Application 2 3 General Information 3 Pump Wiring Instructions 4 Typical Outdoor Prepackaged System 5 Installation and Operation Instructions 6 Maintenance 7 Service Checklist 8 FM2458 0117 Supersedes 1215 NOTICE TO INSTALLER Instructions must remain with installation Product information presented here reflects conditions at time of publication Consult factory regardin...

Page 2: ...otect you against the possibility of electric shock 2 Make certain the electrical service is within reach of the power supply cord 3 Make sure any panels and branch circuits are equipped with proper size fuses and circuit breakers An independent power circuit is recommended sized according to the National Electrical Code for the current shown on the grinder pump nameplate 4 For your protection alw...

Page 3: ...rogressingcavitygrinderpumpisanintermittentdutypumpdesigned for pumping sanitary sewage It is not a dewatering or trash pump FIELD ASSEMBLED INSTALLATION 1 Installation and piping instructions are included with the control panel rail system and basin instructions If pump is being retrofitted to an existing rail system accessory parts may be required Consult the factory and advise make and model of...

Page 4: ...range below horizontal Ranges are based on testing in nonturbulent conditions Range may vary due to watertemperatureandcordshape As tether length increases so does the variance of the pumping range Tether Length inches 5 10 Pumping Range GPM 9 13 5 min max SK305D SK2651 ALARM FLOAT PUMP CONTROL FLOAT TREE FLOAT 406 mm 16 MIN OFF Electrical Data Amps KVA Code Winding Resistance Line to Line Model B...

Page 5: ...CTRICAL PIPE SK2540 SK2533 6 5 8 143 mm 8 3 8 213 mm 5 1 4 133 mm 4 3 8 111 mm 10 1 2 267 mm DIA 22 3 8 568 mm 4 103 mm FIGURE 5 1 1 4 NPT ANTI SIPHON VALVE 1 1 4 NPT CHECK VALVE DISCONNECT 1 1 4 SHUT OFF VALVE HOME OWNER JWA CURB VALVE BOX CHECK VALVE SHUT OFF VALVE MAIN OPTIONAL LOCATION 1 1 4 NPT ANTI SIPHON VALVE POSITIVE DISPLACEMENT GRINDER PUMP 1 1 4 DISCHARGE LINE FIGURE 5A SK2810 1 25 BAL...

Page 6: ...1 Review the drawing in Fig 4 on page 5 and the actual system to become familiar with the components in the packaged grinder pump system Review where the unit will be installed Determine where the power feed inlet pipe and discharge pipe will be located 2 Remove the unit from packing Prepackaged outdoor systems are preassembled at the Zoeller Company and require a minimum of field assembly work Fl...

Page 7: ...ted and replace disc and retainer screws Torque to 63 67 in lbs Replace cutter with the correct shims Install washer and torque hex head bolt to 71 75 in lbs apply Loctite 262 thread lock sealant or equal to bolt threads prior to insertion Check running clearance with pump in vertical position to remove end play Clearance must be between 0 007 and 0 012 to obtain efficient grinding when pump is pu...

Page 8: ...er in cap assembly check valve not installed or malfunctioning B Motor overheats and trips on overload Incorrect voltage hydraulic rotor or cutter blocked negative head discharge lower than intake of pump Defective off float Pump runs continuously at low water level Low oil level in motor shell Pump running at shut off head check valve not installed or malfunctioning C Pump will not shut off Debri...

Reviews: