4
www.zippity-outdoor.com
STEP 2: ASSEMBLE THE HORIZONTAL PICKETS
STEP 2.1
Identify the horizontal top rail - front (F) and the horizontal bottom rail - front (D) as shown below. Pressure fit two
loose rail end caps (B) into the ends of each rail. Set these rails aside for now.
Top rail
will be marked with two pre-
drilled holes on the top of the rail.
Front rails have no pre-drilled holes
at these locations
.
Side rails will have two pre-drilled holes on each end.
B
F
D
STEP 2.2
STEP 2.3
Take two posts (G) and position them so
the routed holes face in towards each
other as shown.
1.
Insert nine horizontal pickets (H) into the
routed holes in one of the posts.
2.
Starting at one end of the opposite post,
guide the pickets into the routed holes in the
post.
NOTE: Identify the top of the screen by finding
the side of the post with pre-drilled hole 2 ¾"
from the end of the post.
2.75 in
2.75 in
4.75 in
4.75 in
G
1
2
H