Step 6 – Commissioning
Check earthing
Earthing continuity must be tested by a qualified technician
using a resistance meter of minimum accuracy of 5% full scale
deflection.
• Ensure electrical power is OFF.
• Verify meter ohms range, connect leads together, reading
should be 0 ohms.
• Hold one test lead to the earth of the power lead.
• Hold the other test lead on a cover fixing screw, then the
tap.
• Verify that in every instance the electrical resistance does
not exceed 1 ohm.
Warning: This appliance must be earthed
Do not turn ON electrical power until instructed. Water must be
available from the tap outlet to prevent damage. Water dispensed
during commissioning may be boiling.
!
FILTER FLUSH
FILTERED
Then, rotate
valve to
FILTERED
Filter flush (Australian models)
Rotate valve to
FILTER FLUSH
FILTER FLUSH
FILTERED
Turn ON mains water.
Allow 5 litres to flow
from vent outlet, to
flush the filter.
Note: Water should NOT
flow into the tank.
Check water connections
Turn ON the mains water supply. Water will flow into the
Hydroboil. Check connections and repair any leaks.
Depress the tap lever into the locked open position. Allow the
tank to fill until water flows from the tap outlet.
Once water is available from the tap, close the tap to stop
water flow.
6.1
6.2
< 1.0 Ω
6.3