Commissioning
8.1
Prerequisites for commissioning
Attention!
1. You must mount and connect the device in accordance with the operating instructions.
2. Double check that all connections are correct.
3. The mains voltage must match the information on the rating plate.
4. The rated current on the rating plate will not be exceeded.
5. Make sure that no persons or objects are in the hazardous area.
8.2
Procedure for commissioning
Sequence
Setting
1
Switch position
“
0
”
(power stack switched off).
This prevents the system from inadvertently starting up before con
fi
guration is complete.
Settings for U/f characteristic can only be made when no motor modulation is present!
2
Set the menu language in the
Quick Info
menu if necessary. To do this, press the
P
key in the overview of the
compartment temperature and then press the Down key several times up to the
Language
menu item.
(Factory setting German:
“
Language D
”
)
3
The factory set values in the
Motorsetup
are for voltage controllable external rotor motors with 230 V / 50 Hz
(
Installation menu). After veri
fi
cation of the motor speci
fi
cations, adjustments are to be adapted, if applicable
(see Rating plate).
4
Switch position
“
Auto
”
(power stack in operation).
Make other settings.
Operating Instructions
Fcontrol
–
model series FTET4/6/10AHMQ-L
Commissioning
L-BAL-E139-GB 2022/03 Index 006