background image

WNS Series horizontal Oil-fired (Gas) Boiler

 

 

 

-4- 

1.4 Preparation for foundation 
      According  to  foundation  sketch,  well  prepare  the  install  foundation  for  boiler  and 
pre-fabrication plate of ladder. 
1.4.1  After  boiler  arrive  in  site,  check  all  parts  according  to  the  packing  list.  Re-check  the 
completeness  of  boiler  set  according  to  the  general  drawing.  Check  whether  there  are  any 
damage and deformation during transport the large boiler components. 
1.4.2 When unload the boiler  large components, can place 8 to 10 piece tubes  below the steel 
plates  of  two  sides  of  bedplate,  pull  it  with  steel  rope  and  make  the  boiler  large  component 
move  slowly  on  the rolled tubes.  At this time should pay attention  to the  location  for placing 
steel rope, insure no any destroy to all boiler parts.

 

 

Install for boiler large components 

      After the boiler is placed on the two strip foundation, it will has some incline, the fore end 
of  axis  centerline  will  higher  than  back  end  for  about  10  to  25mm  (according  to  different 
foundation drawing). It is very convenient for blowing down. 
      After check the level to boiler, add cement to boiler bed support and two wall foot. 

 

Installation for chimney 

The chimney height should be according to the user

s requirements. 

3.1 While assembling chimney, add asbestos rope between flanges, check the perpendicularity 
of chimney through hanging perpendicular line, if there is error, can adjust it by backing piece 
at the connecting location of flange.   
3.2  If  use  steel  cable,  it  can  be  strained  by  screw.  Three  pieces  of  steel  cable  is  uniform 
distributed around a circle, should pay attention to keep three steel cables have the same strain 
force roughly. 

 

Installation for    pipeline, valves and instruments 

4.1  Install  the  pipeline,  valves  and  instruments  according  to  drawings.  Water  pump  is 
connected with water tank, if user has additional requirements, can provide spare water pump. 
4.2  Safety  valve  must  be  assembled  after  hydraulic  testing  and  connected  to  the  tube  for 
dumping  steam  so  as  to  dump  the  steam  to  safety  place.  The  section  area  of  dumping  steam 
pipe  should  not  less  than the section area of the outlet of  safety  valve, the  pipeline  should  be 
arranged to minimize the resistance of blow down and keep draining water smoothly. 
4.3 The blow down pipe should be connected to blowing down tanks or other safety place. In 
order to avoid happening the accident of moving or scald, the pipeline must be fixed. 
4.4  All  steam  pipeline  except  for  main  steam  valve  should  be  assembled  by  user,  there  is  at 
least one elbow at the main steam pipeline, otherwise should add telescopic tube. The pipeline 
must be insulated. 
4.5 The pipes for draining water at the lower position of water level and water level automatic 
controller must be connected to safety place. The cock of water level gauge can rotate quickly 
and has no water leakage. The water level gauge must be assembled with lighting installation. 
4.6  The  dial  panel  of  pressure  gauge  should  be  marked  with  red  line  to  indicate  the  highest 
allowable  working  pressure.  The  cock  of  pressure  gauge  should  rotate  quickly  and  have  no 
water leakage. The drainage of water should be very smooth. The insulation of pressure gauge 
is forbidden. 

 

The other parts installation 

5.1 The oil pump unit should be installed on the bedplate (if oil-fired pump  is  installed inside 
burner, it means oil-transferring pump). 
5.2  The  electrical  control  box  should  be  installed  at  the  position  that  is  convenient  for 
observation burner. 
5.3 The burner will be connected with electrode nozzle of boiler.

 

 

Hydraulic testing 
After finishing the install of boiler pipeline, valves, instrument and so on, check and clean 

the inside surface of boiler, close manhole and hand-hole, conduct hydraulic testing according 

Summary of Contents for WNS Series

Page 1: ...l Gas fired Oil Boiler ZhangjiagangWilfordThermalTechnology Co Ltd Please read this manual carefully before using this machin Only qualified workers can operate this machine If the operation method is...

Page 2: ...ler structure 5 Boiler work principle 7 Operation Manual of Gas Fired Boiler 7 Operation requirements 7 Maintenance of boiler 11 Inspection hydraulic testing for pressure parts 12 Attention for users...

Page 3: ...appendix list product quality certificate one copy Installation description Preparation work before installation Check the completeness of the boiler accessories according to the packing list and the...

Page 4: ...drawings Water pump is connected with water tank if user has additional requirements can provide spare water pump 4 2 Safety valve must be assembled after hydraulic testing and connected to the tube f...

Page 5: ...r boiler water level indication and for the supervision by boiler operator The water level controller is used for transmitting the value of boiler water level The control system will control the runni...

Page 6: ...ecause of some reasons the photo resistance has no sense of light stop burning and send out acoustical light alarm continue post purging for gas fired boiler then stop running boiler Check and find ou...

Page 7: ...ill feed water into the boiler so as to keep it in the normal water level The above mentioned process continues steam will continuously produced by heating the water by absorbing the afterheat of firi...

Page 8: ...iler again according to above mentioned way Running boiler 3 1 Start and running boiler normally 3 1 1 Open the air vent valve on the top of boiler or lift the valve core of safety valve 3 1 2 Start b...

Page 9: ...warming tube should be according to the length diameter of pipeline steam temperature and so on In generally it should not less than ten minutes After the tube is heated open the main steam valve slow...

Page 10: ...it quality 6 9 The photoresistance should be removed for examination testing every three month measure the values of resistance of bright dark Photoresistance type MG41 100A Rated power capacity 100M...

Page 11: ...etter W means week Letter M means month Letter S means season Letter Y means year Blow down of boiler In generally the feeding water contains mineral matter when the water enters into boiler and after...

Page 12: ...nance if less than one month should use wet maintenance 4 1 Dry maintenance Stop running boiler drain off all boiler water remove all dirt inside boiler and clean it bake it by faint fire close all ha...

Page 13: ...ter dropping to working pressure During inspection the pressure should kept no change If find any leakage should well make record for later repairing when the pressure drop to atmosphere After hydraul...

Reviews: